Ellen Ochoa Middle School (previously New Glenridge)

Status
Construction
Funding Model
Traditional
Project Type
New Construction
Budget
$80,000,000
Architect
Grimm + Parker Architecture
General Contractor
MCN Build
Project Manager
Hiwot Haileselassie

School Information

Principal
TBD
Address
5211 Flintridge Drive, Landover Hills, MD 20784
Neighborhood
Landover Hills, Woodlawn
School Board District
District 4
County Council District
District 3
State Legislative District
District 22

 

Project Timeline

Project Scope

New Glenridge Middle School will be a new 1,200-student middle school built within the existing Glenridge Community Park. The school is being constructed on the upper plateau of the park, with access from Flintridge Drive and Gallatin Street. The geothermally heated and cooled building with rooftop solar array will have a new gymnasium and two-story administration wing at the upper part of the park connecting via a school commons with cafeteria and media center to a three-story academic bar nestled into the slope that approaches the park pond. A new playfield, outdoor learning areas, and integration into the existing park pathway system will be part of the project.

News & Announcements

  • The New Glenridge project was recently highlighted in the March 2024 edition of the Department of Capital Programs newsletter. Read the project's update in the newsletter here.
  • The New Glenridge project was highlighted in the September 2023 edition of the Department of Capital Programs newsletter. Read the project's update in the newsletter here.

Project Updates

June 2024

Past Month's Accomplishments 

  • Phase 2, which mainly consists of site work, is on schedule.
  • Site landscaping is in progress.
  • FF&E coordination is underway.

July Lookahead

  • Phase 2 will continue and is expected to be completed in mid-July.
  • The project will reach substantial completion for the building.

April 2024

Past Month's Accomplishments

  • Power, gas, and water hook-ups and start-ups were completed.
  • The full enclosure of the building envelope was completed, along with the installation of the metal panels and brick facade.
  • The gymnasium was completed.
  • Solar panels were installed.
  • Life safety systems installation and testing and HVAC commissioning and functional testing are in progress.
  • Exterior paving and landscaping are underway.

May Lookahead

  • A punch list will be created and punch list work will begin.
  • Final cleaning to begin.
  • Training and closeout procedures will begin.
  • Phase 2 site work will be completed.

November 2023

Past Month's Accomplishments

  • Roofing and all structural work was completed.
  • The gas supply line and underground utilities were completed.
  • The classroom wing build-out was completed.

November Lookahead

  • Completion of the building enclosure is anticipated.
  • Start-up of the mechanical and electrical systems will begin.
  • Installation of lighting, acoustical components, and interior finishes will continue.

Documents & Presentations

Project Update Meeting - 04/02/2024 | Recording; Presentation (English, Spanish, French); Q&A (English, Spanish, French)

Project Update Meeting - 11/08/2023 | Recording; Presentation (English, Spanish, French); Q&A (English, Spanish, French)

Project Update Meeting - 06/06/2023 | Recording; Presentation (English, Spanish, French); Q&A (English, Spanish, French)

Construction Update Meeting - 10/26/2022 | Recording; Presentation (English, Spanish, French); Q&A (English, Spanish, French)

Project Town Hall Meeting - 12/09/2021 | Presentation (English, Spanish, French) | Q&A (English, Spanish, French)

Community Meeting - 10/07/2019Presentation

 Project Planning Committee Meeting - 08/06/2018Presentation

Project Planning Committee Meeting - 07/24/2018 | Presentation

Community Meeting - 07/10/2018 | Flyer; Presentation