December 2023
Past Month’s Accomplishments:
- Existing School Phase 2 & 3 Demolition completed.
30-Day Look Ahead:
- Landscaping at sports fields to start.
- Earthwork for new sports fields to start.
- Mill and overlay at existing parking lot/sidewalks to start.
- Punchlist Completion is in progress.
- Completion of Phase 2 & 3 Demo haul out in progress.
- ESDs 1-3 Plantings in progress.
- Start to final grading of new sports fields in progress.
November 2023
Past Month’s Accomplishments:
- Existing School Phase 2 & 3 Demolition completed.
- Punchlist completion is in progress.
- Existing School Phase 2 & 3 Demolition haul out.
30-Day Look Ahead:
- Phase 2 & 3 of demo hault out to be completed.
- ESDs 1-3 to be begin.
- Final grading of new sports fields to begin.
October 2023
Past Month’s Accomplishments:
- Phase 2 & 3 abatement completed.
- Existing Phase 1 demolition completed.
- Phase 2 & 3 RAZE permit completed.
- Punchlist completion in progress.
- Existing School Phase 2 demolition in progress.
30-Day Look Ahead:
- Existing School Phase 2 demolition to continue.
- Existing Phase 2 demolition to continue.
- ESD 1-3 to begin.
September 2023
Past Month’s Accomplishments:
- Temporary Certificate of Occupancy received for new school on August 4th, 2023.
- Punchlist completion is in progress.
- Existing School Phase 2 Abatement is in progress.
- Existing School Phase 1 Demolition is in progress.
30-Day Look Ahead:
- Phase 1 Demolition is ongoing.
- Phase 2 & 3 RAZE Permit will be delivered.
- Phase 2 & 3 Demolition is ongoing.
August 2023
Past Month’s Accomplishments:
- Learning Stair Woodwork installation completed.
- Sector 2 Dining Flooring completed.
- Programming & Testing of Kitchen Equipment completed.
- Department of Health Inspection, Fire Alarm and Sprinkler Inspection, and final elevator inspection were completed.
- Wall Graphics Installation completed.
- Finishing of Wood Flooring in Dance Room completed.
- Monumental Sign Installation completed.
- Final Paving and Striping of Parking Lots completed.
- Entrance Canopy Metal Panels, Paint, and Downspouts completed.
- Final Waxing in Sector 1 Corridors and Stairways completed.
- East Hardscape & Storage Shed completed.
- Flooring in Sector 2 completed.
- MEP Trim out Sector 2K & Sector 2G completed.
- Abatement of Existing Walker Mill Middle School completed.
- Installation of FF&E for Sector 2 Dining completed.
- Installation of OHD at Learning Stairs completed.
- Installation of Bleachers at Sector 2 Gym completed.
- Installation of Production Studio Equipment completed.
- Installation of Retaining Wall Fence completed.
30-Day Look Ahead:
- Punchlist Walk Remainder of the Building to begin.
- Final Occupancy Inspections to be completed.
- Demolition of Existing School to begin.
July 2023
Past Month’s Accomplishments:
- Furniture & Equipment installation for Sector 1 Academic Classrooms & Offices completed.
- Flooring for Sector 1 Media Center completed.
- Painting of Learning Stair completed.
- Installation of Ceiling Baffles at Learning Stair / Dining completed.
- Setting of Sector 2K Kitchen Equipment completed.
- Installation of Sector 2G Wood Flooring completed.
- Installation of Ceiling Grid and MEP Rough-in at Stairs completed.
- RTU Programming & Testing/Balancing completed.
- Drywall finish at Teacher Support Room under Learning Stairs completed.
- MEP overhead Rough-in for Sector 2G Drama Room completed.
- Point Up Drywall for Sector 2K in Kitchen, Choral, Band, Dance & Corridor completed.
- Entrance Loop Curb & Gutter / Subbase Stone completed.
- TPO Roofing & AVB at Entrance Canopy completed.
- Installation of Bioretention Ponds completed.
- Backfill of Curbs for Sidewalks completed.
- Installation of Shade Structure Footers completed.
- Installation of Toilet Partitions completed.
- Final Grading/Curb & Gutter/Base Pave for North Parking Lot & Bus Loop completed.
- Installation for Ceiling Baffles above Learning Stairs completed.
- Stage, Dance & Learning Stair Wood Flooring completed.
30-Day Look Ahead:
- Installation of Band Room Divider Wall to begin.
- Installation of FF&E Sector 2 Dining to begin.
- Installation of OHD at Learning Stairs Begin to begin.
- Sand, stripe and finish for Sector 2 of the Gym Wood Flooring to begin.
- Installation of Bleachers in Sector 2 of the Gym to begin.
- Installation of Shade Structure Columns & Sail to begin.
- Stage Curtains & Lighting to be completed.
- Installation of Production Studio Equipment to begin.
- Installation of Retaining Wall Fence to begin.
- Punchlist Walk Remainder of the Building is ongoing.
- Final Inspections to be completed.
- Demolition of Existing Building Begin to begin.
June 2023
Past Month’s Accomplishments:
- Installation of casework for Sector 1A on the second floor completed.
- Installation of sprinkler pipe for Sector 2 Dining completed.
- Final connections & control wiring at RTUs completed.
- Overhead MEP for Sector 2G Locker Rooms completed.
- Installation for markerboards & tackboards at Sector 1 Academic Classrooms completed.
- Rough Grade for North Side of Site completed.
- Site Utilities at Main Construction Entrance Road completed.
- Door installation and hardware at Sector 1 on the second floor completed.
- Final touch up / final paint at Sector 1A on the first floor completed.
- Installation of lockers for Sector 1 Academic Classrooms completed.
- Interior glazing throughout building completed.
- Installation for steel, framing & sheathing at entrance canopy completed.
- Ceiling Close-in for Sector 1B on the second floor completed.
- MEP Overhead installation at Sector 2K completed.
- Ceiling Close-in for Sector 1 Media Center completed.
- Ceiling Close-in for Sector 2K Kitchen, Choral, Dining & Corridor completed.
- Final Paint for Sector 1A & 1B on the second floor completed.
- Locker Room Locker Bases in Sector 2G completed.
- Flooring for Sector 2K Choral & Corridor completed.
- Installation for Exterior Overhead Door & Kitchen Coiling Counter Door completed.
- Installation of Dumpster Enclosure completed.
30-Day Look Ahead:
- Sector 2 FF&E Delivery and Installation to begin.
- Stage, Dance & Learning Stair Wood Flooring to begin.
- Installation of Band Room Divider Wall to begin.
- Ceiling Close-in for S2G Drama Room to begin.
- Installation of Lockers for Sector 2G Locker Room to begin.
- Installation of Wall & Floor Tile for Sector 2G Locker Room to begin.
- Flooring at Sector 2 Dining to begin.
- Programming & Testing of Kitchen Equipment to begin.
- Above-Ceiling MEP Rough-In Band Room to be completed.
- Teacher Support Room at Learning Stair to be completed.
- Appliance installation to begin.
- Base Pave Entrance Loop to begin.
- Curb & Gutter / Subbase Stone at North Parking Lot & Bus Loop to begin.
- East Hardscape & Storage Shed to begin.
- Entrance Canopy Metal Panels & Paint to begin.
- Main Entrance Hardscape / Sidewalks to begin.
- Perimeter Permanent Fencing Installation to begin.
- Abatement of Existing Walker Mill Middle School to begin.
May 2023
Past Month’s Accomplishments:
- Base pave for West Parking Lot completed.
- Steel and concrete installation for Learning Stair completed.
- Rough grade for East Side of site completed.
- Installation of ceiling tiles in Sector 1A on first floor and Sector 1B on second floor completed.
- Painting of MEP overhead in Sector 2 of Gym completed.
- Installation of ceramic tile in Sector 1A on second floor completed.
- Installation of interior doors in Sector 1 on first floor completed.
- Installation of gym equipment (backboards, scoreboards etc.) completed.
- Above ceiling close-in inspections in Sector 1A on second floor completed.
- Installation of floor tile in Kitchen and Walk-In Cooler completed.
- Wall framing for Sector 2G in Locker Rooms completed.
- Sidewalks at West Entrance and South Courtyard completed.
- Wiring in Sector 2K for main mechanical room control completed.
- Installation for sprinkler pipe in Sector 1 of the Media Center completed.
- Installation of lights in Sector 2G of the Gym completed.
30-Day Look Ahead:
- Demo existing contractor parking lot to begin.
- Installation of kitchen equipment for Sector 2K in Kitchen to begin.
- Installation of ESD Structures to begin.
- Ceiling Close-in of S1A on second floor to begin.
- Rough Clean of Sector 1 to begin.
- Installation of FF&E in Sector 1B on first floor to begin.
- Inspection of Above-Ceiling in Sector 2K to begin.
- Ceiling Close-In at Sector 2K to begin.
- Paint Stage Ceiling in Sector 2G to begin.
- Wood flooring delivery and acclimate to begin.
- Hanging and finishing walls for Locker Rooms in Sector 2G to begin.
- Celling grid installation of Dining in Sector 2G to begin.
- Ceiling Close-In for Media in Sector 1 to begin.
- Learning stair finishes for Dining in Sector 2 to begin.
April 2023
Past Month’s Accomplishments:
- Stone base for West Parking Lot completed.
- Curb & Gutter and Final Grade for Service Road completed.
- First coat of paint walls for Sector 1A on the second floor completed.
- Ceiling grid in Sector 1A on the second floor completed.
- Educational casework installation for Sector 1A on the first floor completed.
- VCT Flooring installation for Sector 1A on the second floor completed.
- Paint walls for Gym in Sector 2G completed.
- Setting remaining VAVs in Locker Room completed.
- Final waterline connection at water main completed.
- First coat walls & bulkheads in Media Center completed.
- Permanent power to building completed.
- Installation of Sector 1B on first floor ceiling tiles completed.
- Installation of sprinkler pipe for Gym & Locker Rooms in Sector G completed.
- Installation of concrete footers at entrance canopy completed.
30-Day Look Ahead:
- Installation of lockers at Academic Classrooms in Sector 1 to begin.
- Final touch-up / final paint Sector 1A 1st Floor to begin.
- Installation of interior glazing Sector 1 1st Floor to begin.
- Ceiling tile installation of Sector 1A on the first floor to begin.
- Ceiling frame installation for Locker Room in Sector 2G to begin.
- Lighting installation for Gym in Sector 2G to begin.
- Demo of existing contractor parking lot to begin.
- Kitchen equipment installation of Kitchen in Sector 2K to begin.
- Steel installation for entrance canopy to begin.
March 2023
Past Month’s Accomplishments:
- Curb & Gutter and Final Grade at West Parking Lot completed.
- First coat of wall painting for Sector 1A on the second floor completed.
- Ceiling grid for Sector 1A on the second floor completed.
- Educational casework installation for Sector 1B on the first floor completed.
- VCT Flooring installation for Sector 1B on the second floor completed.
- Wall painting for Kitchen in Sector 2K completed.
- Ceiling paint for Gym in Sector 2G completed.
- Set remaining RTUs on roof completed.
- Set chiller completed.
- Installation of gas line down Service Road completed.
- Elevator temp use inspection completed.
- Skylight tube installation completed.
30-Day Look Ahead:
- Installation of VCT flooring for Sector 1A on the second floor to begin.
- Installation of casework for Sector 1A on the second floor to begin.
- Permanent power energy for building to begin.
- Installation of ceiling tiles for Sector 1 on the first floor to begin.
- Installation of ceiling grid for Kitchen in Sector 2K to begin.
- Installation of MEP overhead rough-in for Gym in Sector 2G to begin.
- Final grade and curb/gutter installation down Service Road to begin.
- Base pave of West Parking Lot to continue.
- Installation of concrete footers at the entrance canopy to begin.
February 2023
Past Month’s Accomplishments:
- Underground storm line for West Parking Lot completed.
- Drywall hang and finished walls for Sector 1A on the second floor completed.
- Ceiling grid installation for Sector 1B on the second floor completed.
- Educational casework installation for Sector 1B on the first floor completed.
- VCT Flooring installation for Sector 1 on the first floor completed.
- First coat painted walls for Sector 1B on the second floor completed.
- Drywall hang/finish for Sector 2K completed.
30-Day Look Ahead:
- Underground site utilities in West Parking Lot & Service Road to continue.
- West Parking Lot fill to grade will continue.
- Elevator preparation for temp use inspection will continue.
- Main mechanical room rough-ins for the kitchen in Sector 2K will continue.
- Prime painting for walls in Sector 1A on the second floor will continue.
- Interior wall framing in Sector 2G will continue.
- Ceiling rough-in for Sector 1B on the second floor will continue.
- Skylight tube installation will continue.
- Ceiling pant for Sector 2G will continue.
- Light Fixture installation for Sector 1B on the second floor will continue.
- Ceramic tile installation for Sector 1B on the second floor will begin.
- Flooring installation for Sector 1B on the second floor will begin.
- Casework installation for Sector 1B on the second floor will begin.
- Ceiling grid installation for Sector 1A on the second floor will begin.
- Underground site utilities throughout the project site are ongoing.
- Concrete footer installation at entrance canopy to begin.
- Set final delivery of RTUs to begin.
- West Parking Lot preparation for paving is ongoing.
January 2023
Past Month’s Accomplishments:
- Soil nail retaining wall at the back of school site completed.
- Hanging and finishing of walls on level 2 of Sector 1B completed.
- First delivery of RTUs received.
- Installation of sanitary line running down Service Road completed.
- Ceiling grid installation on level 1 of Sector 1A completed.
- Prime painting of block walls in Sector 2G of Gym completed.
- First coat painting of walls on level 1 of Sectors 1A and 1B completed.
- Installation of underground site utilities in the West Parking Lot and Service Road in progress.
- Installation of elevator at Sector 1 of the Media Center in progress.
- Main mechanical room rough-ins in Sector 2K of Kitchen in progress.
- Overhead MEP rough-in on level 2 of Sector 1A in progress.
- Framing of interior walls in Sector 2G of Gym in progress.
- Installation of light fixtures on level 1 and prime painting of walls on level 2 of Sector 1B in progress.
- Frame bulkheads at skylight tubes in progress.
- One-side hanging of drywall on level 2 of Sector 1A and Sector 2K for Kitchen in progress.
- Overhead MEP rough-in in the Sector 2G for Gym in progress.
30-Day Look Ahead:
- Installation ceramic tile, flooring, and casework on level 1 of Sector 1B to begin.
- Installation of MEP equipment in ceiling tile on level 1 of Sector 1A to begin.
- Installation of ceiling grid on level 2 of Sector 1B to begin.
- Underground site utilities throughout the project site are ongoing.
- Insulation, hanging, and finishing of walls on level 2 of Sector 1A are ongoing.
- Elevator adjuster on Sector 1 for media center is ongoing.
- Installation of concrete footers at the entrance canopy to begin.