Walker Mill Middle School

Status
Complete
Funding Model
P3
Project Type
Replacement
Budget
$69,900,000
Architect
Stantec
General Contractor
Gilbane Building Co.
Project Manager
Brailsford & Dunlavey

School Information

Principal
Erin Cribbs
Address
800 Karen Blvd, Capitol Heights, MD, 20743
Neighborhood
Walker Mill, Capitol Heights
School Board District
District 6
County Council District
District 6
State Legislative District
District 25

Project Timeline

Blueprint Project Timeline.png

Project Scope

Construction of a new 144,000 SF school with a capacity of 1,200 students in the back of the existing Walker Mill Middle School site.

News & Announcements

There are currently no announcements for this project.

Project Updates

Year 2023

December 2023 

Past Month’s Accomplishments: 

  • Existing School Phase 2 & 3 Demolition completed. 

30-Day Look Ahead:  

  • Landscaping at sports fields to start. 
  • Earthwork for new sports fields to start. 
  • Mill and overlay at existing parking lot/sidewalks to start. 
  • Punchlist Completion is in progress. 
  • Completion of Phase 2 & 3 Demo haul out in progress. 
  • ESDs 1-3 Plantings in progress. 
  • Start to final grading of new sports fields in progress. 

November 2023 

Past Month’s Accomplishments: 

  • Existing School Phase 2 & 3 Demolition completed. 
  • Punchlist completion is in progress. 
  • Existing School Phase 2 & 3 Demolition haul out.  

30-Day Look Ahead:  

  • Phase 2 & 3 of demo hault out to be completed. 
  • ESDs 1-3 to be begin. 
  • Final grading of new sports fields to begin. 

October 2023 

Past Month’s Accomplishments: 

  • Phase 2 & 3 abatement completed. 
  • Existing Phase 1 demolition completed. 
  • Phase 2 & 3 RAZE permit completed. 
  • Punchlist completion in progress. 
  • Existing School Phase 2 demolition in progress. 

30-Day Look Ahead:  

  • Existing School Phase 2 demolition to continue. 
  • Existing Phase 2 demolition to continue. 
  • ESD 1-3 to begin. 

September 2023 

Past Month’s Accomplishments: 

  • Temporary Certificate of Occupancy received for new school on August 4th, 2023.  
  • Punchlist completion is in progress. 
  • Existing School Phase 2 Abatement is in progress. 
  • Existing School Phase 1 Demolition is in progress.  

30-Day Look Ahead:  

  • Phase 1 Demolition is ongoing. 
  • Phase 2 & 3 RAZE Permit will be delivered. 
  • Phase 2 & 3 Demolition is ongoing. 

August 2023 

Past Month’s Accomplishments: 

  • Learning Stair Woodwork installation completed. 
  • Sector 2 Dining Flooring completed. 
  • Programming & Testing of Kitchen Equipment completed. 
  • Department of Health Inspection, Fire Alarm and Sprinkler Inspection, and final elevator inspection were completed.
  • Wall Graphics Installation completed. 
  • Finishing of Wood Flooring in Dance Room completed. 
  • Monumental Sign Installation completed. 
  • Final Paving and Striping of Parking Lots completed. 
  • Entrance Canopy Metal Panels, Paint, and Downspouts completed. 
  • Final Waxing in Sector 1 Corridors and Stairways completed. 
  • East Hardscape & Storage Shed completed. 
  • Flooring in Sector 2 completed. 
  • MEP Trim out Sector 2K & Sector 2G completed. 
  • Abatement of Existing Walker Mill Middle School completed. 
  •  Installation of FF&E for Sector 2 Dining completed. 
  • Installation of OHD at Learning Stairs completed. 
  •  Installation of Bleachers at Sector 2 Gym completed. 
  • Installation of Production Studio Equipment completed. 
  • Installation of Retaining Wall Fence completed. 

30-Day Look Ahead:  

  • Punchlist Walk Remainder of the Building to begin. 
  • Final Occupancy Inspections to be completed.  
  • Demolition of Existing School to begin. 

July 2023 

Past Month’s Accomplishments: 

  • Furniture & Equipment installation for Sector 1 Academic Classrooms & Offices completed. 
  • Flooring for Sector 1 Media Center completed. 
  • Painting of Learning Stair completed. 
  • Installation of Ceiling Baffles at Learning Stair / Dining completed. 
  • Setting of Sector 2K Kitchen Equipment completed. 
  • Installation of Sector 2G Wood Flooring completed. 
  • Installation of Ceiling Grid and MEP Rough-in at Stairs completed. 
  • RTU Programming & Testing/Balancing completed. 
  • Drywall finish at Teacher Support Room under Learning Stairs completed. 
  • MEP overhead Rough-in for Sector 2G Drama Room completed. 
  • Point Up Drywall for Sector 2K in Kitchen, Choral, Band, Dance & Corridor completed. 
  • Entrance Loop Curb & Gutter / Subbase Stone completed. 
  • TPO Roofing & AVB at Entrance Canopy completed. 
  • Installation of Bioretention Ponds completed. 
  • Backfill of Curbs for Sidewalks completed. 
  • Installation of Shade Structure Footers completed. 
  • Installation of Toilet Partitions completed. 
  • Final Grading/Curb & Gutter/Base Pave for North Parking Lot & Bus Loop completed. 
  • Installation for Ceiling Baffles above Learning Stairs completed. 
  • Stage, Dance & Learning Stair Wood Flooring completed. 

30-Day Look Ahead:  

  • Installation of Band Room Divider Wall to begin. 
  • Installation of FF&E Sector 2 Dining to begin. 
  • Installation of OHD at Learning Stairs Begin to begin. 
  • Sand, stripe and finish for Sector 2 of the Gym Wood Flooring to begin. 
  • Installation of Bleachers in Sector 2 of the Gym to begin. 
  • Installation of Shade Structure Columns & Sail to begin. 
  • Stage Curtains & Lighting to be completed. 
  • Installation of Production Studio Equipment to begin. 
  • Installation of Retaining Wall Fence to begin. 
  • Punchlist Walk Remainder of the Building is ongoing. 
  •  Final Inspections to be completed. 
  • Demolition of Existing Building Begin to begin. 

June 2023 

Past Month’s Accomplishments: 

  • Installation of casework for Sector 1A on the second floor completed. 
  • Installation of sprinkler pipe for Sector 2 Dining completed. 
  • Final connections & control wiring at RTUs completed. 
  • Overhead MEP for Sector 2G Locker Rooms completed. 
  • Installation for markerboards & tackboards at Sector 1 Academic Classrooms completed. 
  • Rough Grade for North Side of Site completed. 
  • Site Utilities at Main Construction Entrance Road completed. 
  • Door installation and hardware at Sector 1 on the second floor completed. 
  • Final touch up / final paint at Sector 1A on the first floor completed. 
  • Installation of lockers for Sector 1 Academic Classrooms completed. 
  • Interior glazing throughout building completed. 
  • Installation for steel, framing & sheathing at entrance canopy completed. 
  • Ceiling Close-in for Sector 1B on the second floor completed. 
  • MEP Overhead installation at Sector 2K completed. 
  • Ceiling Close-in for Sector 1 Media Center completed. 
  • Ceiling Close-in for Sector 2K Kitchen, Choral, Dining & Corridor completed. 
  • Final Paint for Sector 1A & 1B on the second floor completed. 
  • Locker Room Locker Bases in Sector 2G completed. 
  • Flooring for Sector 2K Choral & Corridor completed. 
  • Installation for Exterior Overhead Door & Kitchen Coiling Counter Door completed. 
  • Installation of Dumpster Enclosure completed. 

30-Day Look Ahead:  

  • Sector 2 FF&E Delivery and Installation to begin. 
  • Stage, Dance & Learning Stair Wood Flooring to begin. 
  • Installation of Band Room Divider Wall to begin. 
  • Ceiling Close-in for S2G Drama Room to begin. 
  • Installation of Lockers for Sector 2G Locker Room to begin. 
  • Installation of Wall & Floor Tile for Sector 2G Locker Room to begin. 
  • Flooring at Sector 2 Dining to begin. 
  • Programming & Testing of Kitchen Equipment to begin. 
  • Above-Ceiling MEP Rough-In Band Room to be completed. 
  • Teacher Support Room at Learning Stair to be completed. 
  • Appliance installation to begin. 
  • Base Pave Entrance Loop to begin. 
  • Curb & Gutter / Subbase Stone at North Parking Lot & Bus Loop to begin.  
  • East Hardscape & Storage Shed to begin. 
  • Entrance Canopy Metal Panels & Paint to begin. 
  • Main Entrance Hardscape / Sidewalks to begin. 
  • Perimeter Permanent Fencing Installation to begin. 
  • Abatement of Existing Walker Mill Middle School to begin. 

May 2023 

Past Month’s Accomplishments: 

  • Base pave for West Parking Lot completed. 
  • Steel and concrete installation for Learning Stair completed. 
  • Rough grade for East Side of site completed. 
  • Installation of ceiling tiles in Sector 1A on first floor and Sector 1B on second floor completed. 
  • Painting of MEP overhead in Sector 2 of Gym completed. 
  • Installation of ceramic tile in Sector 1A on second floor completed. 
  • Installation of interior doors in Sector 1 on first floor completed. 
  • Installation of gym equipment (backboards, scoreboards etc.) completed. 
  • Above ceiling close-in inspections in Sector 1A on second floor completed. 
  • Installation of floor tile in Kitchen and Walk-In Cooler completed. 
  • Wall framing for Sector 2G in Locker Rooms completed. 
  • Sidewalks at West Entrance and South Courtyard completed. 
  • Wiring in Sector 2K for main mechanical room control completed. 
  • Installation for sprinkler pipe in Sector 1 of the Media Center completed. 
  • Installation of lights in Sector 2G of the Gym completed. 

30-Day Look Ahead:  

  • Demo existing contractor parking lot to begin. 
  • Installation of kitchen equipment for Sector 2K in Kitchen to begin. 
  • Installation of ESD Structures to begin.  
  • Ceiling Close-in of S1A on second floor to begin. 
  • Rough Clean of Sector 1 to begin. 
  • Installation of FF&E in Sector 1B on first floor to begin.  
  • Inspection of Above-Ceiling in Sector 2K to begin. 
  • Ceiling Close-In at Sector 2K to begin. 
  • Paint Stage Ceiling in Sector 2G to begin. 
  • Wood flooring delivery and acclimate to begin. 
  • Hanging and finishing walls for Locker Rooms in Sector 2G to begin. 
  • Celling grid installation of Dining in Sector 2G to begin. 
  • Ceiling Close-In for Media in Sector 1 to begin. 
  • Learning stair finishes for Dining in Sector 2 to begin. 

April 2023 

Past Month’s Accomplishments:  

  • Stone base for West Parking Lot completed. 
  • Curb & Gutter and Final Grade for Service Road completed. 
  • First coat of paint walls for Sector 1A on the second floor completed. 
  • Ceiling grid in Sector 1A on the second floor completed. 
  • Educational casework installation for Sector 1A on the first floor completed. 
  • VCT Flooring installation for Sector 1A on the second floor completed.  
  • Paint walls for Gym in Sector 2G completed. 
  • Setting remaining VAVs in Locker Room completed. 
  • Final waterline connection at water main completed. 
  • First coat walls & bulkheads in Media Center completed. 
  • Permanent power to building completed. 
  • Installation of Sector 1B on first floor ceiling tiles completed. 
  • Installation of sprinkler pipe for Gym & Locker Rooms in Sector G completed. 
  • Installation of concrete footers at entrance canopy completed. 

30-Day Look Ahead:  

  • Installation of lockers at Academic Classrooms in Sector 1 to begin.  
  • Final touch-up / final paint Sector 1A 1st Floor to begin.  
  • Installation of interior glazing Sector 1 1st Floor to begin.  
  • Ceiling tile installation of Sector 1A on the first floor to begin.  
  • Ceiling frame installation for Locker Room in Sector 2G to begin.  
  • Lighting installation for Gym in Sector 2G to begin.  
  • Demo of existing contractor parking lot to begin.  
  • Kitchen equipment installation of Kitchen in Sector 2K to begin.  
  • Steel installation for entrance canopy to begin. 

March 2023 

Past Month’s Accomplishments: 

  • Curb & Gutter and Final Grade at West Parking Lot completed. 
  • First coat of wall painting for Sector 1A on the second floor completed. 
  • Ceiling grid for Sector 1A on the second floor completed. 
  • Educational casework installation for Sector 1B on the first floor completed. 
  • VCT Flooring installation for Sector 1B on the second floor completed. 
  • Wall painting for Kitchen in Sector 2K completed. 
  • Ceiling paint for Gym in Sector 2G completed. 
  • Set remaining RTUs on roof completed. 
  • Set chiller completed. 
  • Installation of gas line down Service Road completed. 
  • Elevator temp use inspection completed. 
  • Skylight tube installation completed. 

30-Day Look Ahead: 

  • Installation of VCT flooring for Sector 1A on the second floor to begin. 
  • Installation of casework for Sector 1A on the second floor to begin. 
  • Permanent power energy for building to begin. 
  • Installation of ceiling tiles for Sector 1 on the first floor to begin. 
  • Installation of ceiling grid for Kitchen in Sector 2K to begin. 
  • Installation of MEP overhead rough-in for Gym in Sector 2G to begin.  
  • Final grade and curb/gutter installation down Service Road to begin. 
  • Base pave of West Parking Lot to continue. 
  • Installation of concrete footers at the entrance canopy to begin. 

February 2023 

Past Month’s Accomplishments: 

  • Underground storm line for West Parking Lot completed. 
  • Drywall hang and finished walls for Sector 1A on the second floor completed. 
  • Ceiling grid installation for Sector 1B on the second floor completed. 
  • Educational casework installation for Sector 1B on the first floor completed. 
  • VCT Flooring installation for Sector 1 on the first floor completed. 
  • First coat painted walls for Sector 1B on the second floor completed. 
  • Drywall hang/finish for Sector 2K completed. 

30-Day Look Ahead: 

  • Underground site utilities in West Parking Lot & Service Road to continue. 
  • West Parking Lot fill to grade will continue. 
  • Elevator preparation for temp use inspection will continue. 
  • Main mechanical room rough-ins for the kitchen in Sector 2K will continue. 
  • Prime painting for walls in Sector 1A on the second floor will continue. 
  • Interior wall framing in Sector 2G will continue. 
  • Ceiling rough-in for Sector 1B on the second floor will continue. 
  • Skylight tube installation will continue. 
  • Ceiling pant for Sector 2G will continue. 
  • Light Fixture installation for Sector 1B on the second floor will continue. 
  • Ceramic tile installation for Sector 1B on the second floor will begin.  
  • Flooring installation for Sector 1B on the second floor will begin. 
  • Casework installation for Sector 1B on the second floor will begin. 
  • Ceiling grid installation for Sector 1A on the second floor will begin. 
  • Underground site utilities throughout the project site are ongoing. 
  • Concrete footer installation at entrance canopy to begin. 
  • Set final delivery of RTUs to begin. 
  • West Parking Lot preparation for paving is ongoing. 

January 2023 

Past Month’s Accomplishments: 

  • Soil nail retaining wall at the back of school site completed. 
  • Hanging and finishing of walls on level 2 of Sector 1B completed. 
  • First delivery of RTUs received. 
  • Installation of sanitary line running down Service Road completed. 
  • Ceiling grid installation on level 1 of Sector 1A completed. 
  • Prime painting of block walls in Sector 2G of Gym completed. 
  • First coat painting of walls on level 1 of Sectors 1A and 1B completed. 
  • Installation of underground site utilities in the West Parking Lot and Service Road in progress. 
  • Installation of elevator at Sector 1 of the Media Center in progress. 
  • Main mechanical room rough-ins in Sector 2K of Kitchen in progress. 
  • Overhead MEP rough-in on level 2 of Sector 1A in progress. 
  • Framing of interior walls in Sector 2G of Gym in progress. 
  • Installation of light fixtures on level 1 and prime painting of walls on level 2 of Sector 1B in progress. 
  • Frame bulkheads at skylight tubes in progress. 
  • One-side hanging of drywall on level 2 of Sector 1A and Sector 2K for Kitchen in progress. 
  • Overhead MEP rough-in in the Sector 2G for Gym in progress. 

30-Day Look Ahead: 

  • Installation ceramic tile, flooring, and casework on level 1 of Sector 1B to begin. 
  • Installation of MEP equipment in ceiling tile on level 1 of Sector 1A to begin. 
  • Installation of ceiling grid on level 2 of Sector 1B to begin. 
  • Underground site utilities throughout the project site are ongoing. 
  • Insulation, hanging, and finishing of walls on level 2 of Sector 1A are ongoing. 
  • Elevator adjuster on Sector 1 for media center is ongoing. 
  • Installation of concrete footers at the entrance canopy to begin. 

Year 2022

December 2022 

Past Month’s Accomplishments: 

  • Installation of stairs 1 and 3 completed. 
  • Interior MEP in-wall rough-ins at sector 2K and on level 2 of sectors 1A and 1B completed. 
  • Installation of storefront doors for all of exterior completed. 
  • Hanging of one side of drywall and insulation inspection on level 2 of sector 1B completed. 
  • Installation of ACT ceiling grid and first coat paint walls on level 1 of sector 1B completed. 
  • Prime painting of walls on level 1 of sector 1A on the first floor completed. 
  • Ductwork in the high media area of sector 1 completed. 
  • Caulking of exterior windows completed. 
  • Stormtech detention system in west parking lot completed. 
  • Interior MEP overhead rough ins on level 2 of sector 1A in progress. 
  • Construction of soil nail retaining wall at back of school site in progress. 
  • Installation of underground site utilities in west parking lot and service road in progress. 
  • Installation of elevator at sector 1 for media center in progress. 
  • Main mechanical room rough-ins in sector 2K of kitchen in progress. 
  • Hanging and finishing of walls on level 2 of sector 1B in progress. 
  • Overhead MEP rough-ins on level 2 of sector 1A in progress. 
  • Framing of interior walls in sector 2G of gym in progress 

30-Day Look Ahead: 

  • Installation of light fixtures on level 1 of sector 1B to begin. 
  • Installation of underground site utilities throughout the project site is ongoing. 
  • First coat interior paint and ceiling grid installation on level 1 of sector 1A to begin. 
  • Installation of soil nail retaining wall to be completed. 
  • Hanging and finishing of walls and prime paint on level 2 of sector 1B is ongoing. 
  • Elevator adjuster for sector 1 of media center to begin. 
  • One side hang walls in section 2K of kitchen to begin. 

November 2022 

Past Month’s Accomplishments: 

  • Interior MEP overhead rough-ins on level 2 of sector 1B completed. 
  • Interior stud wall framing on level 2 for sector 1A and 2K completed. 
  • Hanging and finishing drywall and prime paint walls on level 1 of Sector 1B completed. 
  • Hanging of drywall on level 1 and installation of door frames on level 2 of sector 1A completed. 
  • Interior MEP overhead and in-wall rough-ins for sectors 1A and 1B in progress. 
  • Soil nail retaining wall at back of school site in progress. 
  • Installation for stairs 1 and 3 and elevator in sector 1 of media center in progress. 
  • Underground site utilities for west parking lot in progress. 
  • Caulking of exterior windows and installation of exterior storefront doors in progress. 
  • Main mechanical room rough-ins for sector 2K in progress. 

30-Day Look Ahead: 

  • Underground site utilities throughout the project site is ongoing. 
  • Hanging of one-sided drywall and first coat interior paint in Sector 1B to begin. 
  • Soil nail retaining wall installation to continue. 
  • Drywall finishing and prime paint on level 1 of Sector 1A to begin. 
  • MEP rough-ins in Sector 2K for mechanical and electrical rooms to be completed. 
  • Installation of ACT ceiling grid on level 1 of sector 1B to begin. 

October 2022 

Past Month’s Accomplishments: 

  • Spray fireproofing and in-wall MEP rough-ins on various levels of Sector 1A completed. 
  • One side hanging and in-wall insulation on level 1 of Sector 1B completed. 
  • Installation of welded door frames, exterior windows, and TPO roofing throughout Sector 1 completed. 
  • Installation of interior CMU block walls at sector 2G completed. 
  • Interior stud wall framing at sector 2K completed. 
  • Installation of RTU curbs completed. 
  • Interior MEP overhead rough-in on level 2 of sector 1A and 1B in progress. 
  • Interior stud wall framing in sectors 1A and 2K in progress. 
  • Hanging of one side drywall on level 1 of sector 1B in progress. 
  • Soil nail retaining wall at back of school site in progress. 
  • Installation of stairs 1 and 3 in progress. 
  • Underground site utilities in west parking lot in progress. 
  • Installation of exterior windows for sector 2 in progress. 

30-Day Look Ahead: 

  • Underground site utilities throughout the project site to continue. 
  • Hanging of one side drywall in Sector 1A to begin. 
  • Installation of soil nail retaining wall to continue. 
  • Hanging of second side drywall and drywall finishing for all walls on level 1 of Sector 1B to begin. 
  • MEP rough-in for mechanical and electrical rooms in Sector 2K to begin. 
  • Installation of knock down and welded door frames in Sector 1 to begin. 

September 2022 

Past Month’s Accomplishments: 

  • Interior MEP overhead rough-in in for building in Sector 1A completed. 
  • Spray fireproofing and installation of ceiling metal lath in building for Sector 2K completed. 
  • Installation of exterior metal wall panels and CMU support for steel in building of Sector 2G completed. 
  • Interior stud wall framing and spray fireproofing on level 2 for building in Sector 1B completed. 
  • Ceiling metal lath installation on level 2 of building in Sector 2A completed. 
  • Installation of stair 2 completed. 
  • Pouring of concrete stage and installation of water meter vault completed. 
  • Interior MEP overhead rough-in on level 2 of building for Sector 1B in progress. 
  • Installation of interior CMU block walls at building in Sector 2G in progress. 
  • Installation of TPO roofing and windows in building for Sector 1 in progress. 
  • Interior stud wall framing in building for Sector 2K in progress. 
  • One-side drywall installation on level 1 of building for Sector 1B in progress. 
  • Installation of soil nail retaining wall in progress. 

30-Day Look Ahead: 

  • Spray fireproofing, interior stud wall framing, and overhead MEP rough-in on level 2 of building in Sector 1A to begin. 
  • Installation of underground site utilities throughout the project site is ongoing. 
  • Hanging of one side drywall on level 1 of building in Sector 1A to begin. 
  • Installation of windows in building for Sector 2 to begin. 
  • Installation of door frames in building for Sector 1 to begin. 
  • Installation of soil nail retaining wall to continue. 

August 2022 

Past Month’s Accomplishments: 

  • Spraying of fireproofing on level 1 of building for Sector 1A completed. 
  • Interior stud wall framing at building for Sector 1A completed. 
  • Laying of exterior brick at building Sectors 1A and 2G completed. 
  • Ceiling metal lath installation on level 2 of building Sector 1B completed. 
  • Installation of Washington Suburban Sanitary Commission (WSSC) water main division valve on Karen Blvd. completed. 
  • Interior CMU block walls in building Sector 2K completed. 
  • Interior MEP overhead rough-in at building Sector 1A in progress. 
  • TPO roofing installation in building Sector 1 in progress. 
  • Spraying of fireproofing and interior stud wall framing on second floor of building in Sector 1B in progress. 
  • Installation of interior CMU block walls and exterior wall panels at building Sector 2G in progress. 
  • Installation of ceiling metal lath in building for Sector 2K in progress. 

30-Day Look Ahead: 

  • Installation of metal ceiling lath at building for Sector 1A is ongoing. 
  • MEP overhead rough-in on level 2 of building Sector 1B is ongoing. 
  • TPO roof installation at building Sector 2 is ongoing. 
  • Underground site utilities throughout the project site to begin. 
  • Construction of site retaining wall installation to begin. 

July 2022 

Past Month’s Accomplishments: 

  • Roof panel installation at building sectors 1A and 2G completed. 
  • Interior stud wall framing at sector 1B completed. 
  • Installation of exterior brick at sector 1B and 2K completed. 
  • Wall layout at sector 1A completed. 
  • Installation of interior MEP overhead rough in sector 1B in progress. 
  • Spraying of fireproofing at building sector 1A in progress. 
  • Installation of interior CMU block walls at building sectors 2K and 2G in progress. 
  • Installation of exterior wall panels at sector 2K in progress. 
  • Installation of CMU support steel at sector 2G in progress. 

30-Day Look Ahead: 

  • Installation of metal ceiling lath at building sector 1B to begin. 
  • Interior wall framing, MEP overhead rough-in, and TPO roof installation at sector 1A to begin. 
  • Exterior brick ledge at sector 1A to be completed. 
  • Installation of exterior wall panels at sector 1B to be completed. 
  • Installation of underground site utilities throughout the project site to begin. 
  • Installation of underground water line division valve on Karen Blvd to be completed. 

June 2022 

Past Month’s Accomplishments: 

  • Installation of roof panels for building and perimeter knee wall installation at building sectors 1B and 2K completed. 
  • Secondary steel installation in building sector 1A completed. 
  • Primary and secondary steel installation in building sector 2G completed. 
  • Fireproofing on first floor of building sector 1B completed. 
  • Building perimeter knee wall installation for sectors 1A and 2G in progress. 
  • Installation of interior MEP overhead rough-in in for building sector 1B in progress. 
  • Interior wall framing at building sector 1B in progress. 
  • Interior wall layout building, fireproofing, and installation of roof panels at building sector 1A in progress. 
  • Installation of CMU and elevator shaft for building sector 2K in progress. 

30-Day Look Ahead: 

  • Installation of roof panels at building sector 1A to be completed. 
  • Installation of roof panels at building sector 2G to be completed. 
  • Exterior brick walls and installation of ceiling metal lath in building sector 1B to begin. 
  • Exterior wall panels for building sectors 1B & 1A to begin. 
  • Installation of CMU in building sector 2G to begin. 

May 2022 

Past Month’s Accomplishments: 

  • Steel erection and detailing of steel in building sector 1A completed. 
  • Secondary steel in building sector 1B completed. 
  • Steel erection, detailing, and secondary steel in building sector 2K completed. 
  • Concrete slab on grade at building sector 2G completed. 
  • Elevated concrete slabs at building sectors 1A and 1B completed. 
  • Soil verification nails for retaining wall completed. 
  • Building perimeter knee wall installation for building sector 1B in progress. 
  • Installation of interior MEP hangers at building sectors 1A and 1B in progress. 
  • Interior wall layout and installation of roof panels for building sector 1B in progress. 
  • Installation of roof purlin framing at building sector 1A in progress. 

30-Day Look Ahead: 

  • Installation of roof panels at building sector 1B to be completed. 
  • Installation of roof panels at building sector 1A to continue. 
  • Construction of exterior wall panels at building sectors 1A and 1B to begin. 
  • Primary and secondary steel at building sector 2G to be completed. 
  • Interior MEP hangers at first floor of sector 1A to be completed. 
  • Fireproofing at first floor of building sectors 1A and 1B to begin. 
  • Installation of roof panels at building sector 2K to begin. 

April 2022 

Past Month’s Accomplishments: 

  • Steel erection and detailing of steel in sector 1B completed. 
  • Sector 2K underground MEP and slab on grade concrete pour completed. 
  • Concrete building foundations at sector 2G completed. 
  • Steel erection in sector 1A in progress. 
  • Underground MEP at sector 2G in progress. 
  • Prepping for elevated concrete deck pour at sector 1B in progress. 

30-Day Look Ahead: 

  • Steel erection at sector 2K to begin. 
  • Metal deck and detailing at sector 1A to begin. 
  • Pouring of elevated concrete deck at sector 1B to begin. 
  • Pouring of slab on grade at sector 2G to begin. 
  • Secondary steel install at sector 1B to begin. 

March 2022 

Past Month’s Accomplishments: 

  • Rough in MEP underground utilities in sector 1A completed. 
  • Deliveries of structural steel completed. 
  • Pouring of concrete slab on grade in sector 1B completed. 
  • Pouring of concrete slab on grade in sector 1A completed. 
  • Steel erection in sector 1B in progress. 
  • Installation of concrete building foundations and rough in of MEP underground utilities in sector 2K in progress. 
  • Installation of concrete building foundations in sector 2G in progress. 

30-Day Look Ahead: 

  • Detailing of steel in sector 1B to begin. 
  • Steel erection in sector 1A to begin. 
  • Concrete building foundations in sector 2K to be completed. 
  • Pouring of concrete slab on grade in sector 2K to begin. 
  • Finish concrete building foundations in sector 2G to be completed. 

February 2022 

Past Month’s Accomplishments: 

  • Rough in MEP underground utilities in classroom wing 1B completed. 
  • Preparation for SOG pour-in for classroom wing 1B is completed. 
  • Pouring of concrete foundation footings, piers & walls at classroom wing 1A completed. 
  • Preparation of building pad in building wings 2G and 2K completed. 
  • Installation of site haul roads completed. 
  • Rough in MEP underground utilities for classroom wing 1A in progress. 
  • Installation of concrete building foundations for wing 2K in progress. 
  • Rough in MEP underground utilities for wing 2K in progress. 
  • Deliveries of structural steel in progress. 

30-Day Look Ahead: 

  • Pouring of concrete slab on grade in classroom wing 1B to be completed. 
  • Preparation and pouring of concrete slab for grade in classroom wing 1A to be completed. 
  • Structural steel erection in classroom wing 1B to begin. 
  • Concrete building foundations in building wing 2G to begin. 
  • Concrete building foundations in building wing 2K to be completed. 
  • Receiving of structural steel beams and columns deliveries to begin. 

January 2022 

Past Month’s Accomplishments: 

  • Concrete foundations at classroom wing 1B completed. 
  • Removal of surcharge dirt at classroom wings 2G and 2K completed. 
  • Installation of site haul road and laydown areas in progress. 
  • First delivery of steel joists and metal deck received. 
  • MEP underground at classroom wing 1B in progress. 
  • Pouring of concrete foundation footings, piers & walls at classroom wing 1A in progress. 

30-Day Look Ahead: 

  • Preparing of building pad in Building Wings 2G and 2K underway. 
  • Classroom wing 1A foundations to be completed. 
  • Underground MEP at wing 1A to begin. 
  • Pouring of concrete slab on grade at wing 1B to begin. 
  • Pouring of foundations at wing 2K to begin. 
  • Structural steel beams/columns deliveries to be received. 

Year 2021

December 2021 

Past Month’s Accomplishments: 

  • Stripping of surcharge soil and preparing of building pad for concrete foundations at Classroom Wings 1A and 1B completed. 
  • Tree removal at the SW corner of the site is completed. 
  • Installation of site haul road and laydown areas completed. 
  • Pouring of concrete foundation footings, piers, and walls at Classroom Wing 1B in progress. 
  • Surcharge and settlement of building pad for Wings 2G and 2K in progress. 

30-Day Look Ahead: 

  • Surcharge and settlement at building pad for Wing 2G and 2K to be completed. 
  • Pouring of concrete foundations for Classroom Wings 1A and 1B to begin. 
  • Stripping soil of building pads for Wing 2G and 2K to begin. 
  • Installation of site access roads and laydown areas to begin. 

November 2021 

Past Month’s Accomplishments: 

  • Imported fill for surcharge/settlement at building pad completed. 
  • Temporary power to construction entrance for security camera and wheel wash station installed. 
  • Construction of the haul road around building pad and material laydown area is in progress. 

30-Day Look Ahead: 

  • Surcharging/settlement building pad and monitoring of plates by geotechnical engineer ongoing. 
  • Surcharge will reach final settlement. 
  • Cutting and filling to bring building pad to subgrade will begin. 
  • Any necessary undercutting of subgrade will be completed. 

October 2021 

Past Month’s Accomplishments: 

  • Erosion and sediment control measures installed at the site perimeter. 
  • Construction of site sediment trap completed. 
  • Stripping of topsoil and rough grading of site in progress. 

30-Day Look Ahead: 

  • Stripping of topsoil to be completed. 
  • Importing of dirt for building pad to begin. 
  • Tree removal to begin. 

August 2021 

Past Month’s Accomplishments: 

  • Site perimeter surveying and fencing completed. 
  • Installation of temporary electricity to the jobsite completed. 
  • Perimeter erosion and sediment control measures in progress. 

30-Day Look Ahead: 

  • Site perimeter erosion and sediment control measures to be completed. 
  • Sediment trap installation to begin. 
  • Rough grading of the site to begin. 
  • Surcharge of the site and hauling of dirt into the site to commence. 

Documents & Presentations

Project Fact Sheet

Project Update Meeting - 05/08/2023 | Recording; Presentation (English, Spanish, French); Q&A (English, Spanish, French)

Construction Update Meeting - 10/12/2022 | Presentation (English, Spanish, French)

Community Investment Program Town Hall - 04/2021 | Recording; Presentation (English, Spanish, French)

Construction Site Logistics Town Hall - 01/25/2021 | Presentation (English, Spanish, French)

PGCPS Alternative Construction Finance Program Town Hall - 12/17/2020 | Presentation (English, Spanish, French)