January 2022
Past Month’s Accomplishments:
- 95% of concrete slab on grade in building sectors 1A and 1B complete.
- Concrete building foundations at building sector 1A complete.
- Under slab utilities at building sector 1A complete.
- Concrete slab on grade at sector 1A complete.
- Pouring of concrete building foundation footings, piers & walls at building sectors 2G and 2K in progress.
- Rough in under slab utilities at building sector 2G in progress.
30-Day Look Ahead:
- Pouring of concrete building foundations at sector 2G is ongoing.
- Rough in under slab utilities at sectors 2K and 2G to continue.
- Pouring of concrete slab on grade at sectors 2G and 2K is ongoing.
February 2022
Past Month’s Accomplishments:
- 90% of concrete slab on grade in building Sector 2K and 2G completed.
- Rough in under slab MEP utilities at building Sectors 2K and 2G completed.
- Steel deliveries completed.
- Shaking out building structural steel to ready for steel erection in progress.
30-Day Look Ahead:
- Steel erection at sectors 1A and 2G is ongoing
March 2022
Past Month’s Accomplishments:
- All underslab plumbing and electrical completed.
- All concrete slabs on grade completed.
- Erection of steel in the Kitchen and Gym sectors completed.
- Erection of classroom steel in building sectors 1A and 1B in progress.
- Form/pour stage ramp/slab and foundation wall damp-roofing and backfill in progress.
30-Day Look Ahead:
- Building perimeter knee wall framing and AVB at sectors 1A, 2K, and 2G is ongoing.
- Roof parapet framing for east commons is ongoing.
- MEP hangers and interior wall layout at sector 1A to begin.
- Structural steel erection in sectors 1A and 1B to continue.
- Façade metal panel deliveries to begin.
- Slab on deck pours at 1A to continue.
April 2022
Past Month’s Accomplishments:
- Building perimeter knee wall framing and AVB at sector 2K completed.
- MEPF hangers and interior wall layout sector 1A completed.
- Structural steel erection in sectors1A and 1B completed.
- Exterior metal panel deliveries completed.
- Elevated concrete deck pours at sector 1A completed.
- Install roof panels at sectors 2K and 2G completed.
- Metal decking and MEPF elevated concrete decks rough in sector 1B in progress.
- Interior CMU block walls in sectors 2G and 2K in progress.
- Forming and pouring of concrete stage ramp in progress.
- Building foundation wall waterproofing and backfill in progress.
- Building perimeter exterior brick knee wall sectors 2K and 2G in progress.
30-Day Look Ahead:
- Building perimeter knee wall framing and AVB at sectors 1A, 1B, and 2G is ongoing.
- Roof panel install at sectors 1A and 1B is ongoing.
- MEPF hangers and interior wall layout Sector 1B to continue.
- Exterior wall metal panel deliveries are ongoing.
- Elevated concrete deck pours at sector 1B to begin.
- Site storm water utilities install to begin.
- Interior CMU block elevator shaft walls to begin.
May 2022
Past Month’s Accomplishments:
- Building perimeter exterior knee wall framing and MEPF hangers at building sectors 1A and 1B completed.
- Interior CMU block walls in the kitchen area completed.
- Interior wall layout building and elevated concrete deck pours at sector 1B completed.
- Interior CMU block walls in elevator shaft and sector 2G in progress.
- Site storm water utilities installation in progress.
- Pouring of concrete stage ramp in progress.
- Building foundation wall waterproofing and backfill in progress.
30-Day Look Ahead:
- Installation of hat channel system and interior wall framing in building sectors 1A, 1B, and 2K is ongoing.
- MEP ceiling rough-in in building sector 1B is ongoing.
- MEPF hanger installation and roof panel installation in building sectors 1A and 1B to be completed.
- Interior CMU block walls in building sector 2G to be completed.
- Exterior brick around the perimeter of the building to be completed.
- Exterior wall panel installation in building sectors 2K and 2G is ongoing.
- Installation of the site storm utility to be completed.
June 2022
Past Month’s Accomplishments:
- MEPF hangers and interior wall layout and fire proofing in building sector 1B completed.
- Installation of roof panels in building sectors 1A and 1B completed.
- Forming and pouring of concrete stage and ramp completed.
- Exterior wall panels in building sector 2K completed.
- Framing out of interior walls on first floor and ceiling hat channels in building sector 1A completed.
- Underground site storm water infrastructure at parking lot area completed.
- Interior CMU block elevator shaft walls completed.
- Ceiling hat channel installation and MEPF rough-in in sector 1B in progress.
- Site storm water utilities installation in the soccer field in progress.
- Interior CMU block walls in building sector 2G in progress.
- Building foundation wall waterproofing and backfill in progress.
- MEPF hangers and interior wall layout building in level 2 and fireproofing ceiling lath in sectors 1A and 1B in progress.
30-Day Look Ahead:
- Installation of hat channel system in building sectors 1A, 1B, and 2K is ongoing.
- Interior wall framing in building sectors 1B and 2K is ongoing.
- MEP ceiling rough-in in building sector 1B is ongoing.
- Installation of MEPF hangers in level 2 of building sectors 1A and 1B to be completed.
- Interior CMU block walls in building sector 2G to be completed.
- Exterior brick around the perimeter of the building to be completed.
- Installation of exterior wall panels in building sector 2G to continue.
- Installation of site storm utilities to continue.
July 2022
Past Month’s Accomplishments:
- MEPF hangers installation and interior wall layout at building sectors 2A and 2B completed.
- Installation and pouring of concrete stair tread infills at stair 2 completed.
- Spraying of fireproofing and ceiling hat channel installation at building sector 1B completed.
- Exterior wall panel installation at building sector 2G completed.
- Framing out of interior walls on level 1 of building sector 1B completed.
- Ceiling metal lath installation on level 2 of building sector 1B completed.
- Underground site storm water infrastructure at parking lot area completed.
- Interior CMU block walls in the gym completed.
- MEP above ceiling rough-in and exterior brick installation at building sector 1A completed.
- Site storm water utilities installation at soccer field completed.
- Installation of ceiling metal lath, MEPF hangers, and interior wall layout on level 2 of building sector 1B in progress.
- Installation of site underground sanitary piping in progress.
- Installation of exterior brick, building foundation wall waterproofing, and backfill at building sector 1B in progress.
- Spraying of fireproofing ceiling lath at building sector 1A in progress.
- MEPF rough-in at building sector 1B, east commons, and gym in progress.
- Installation of TPO roofing at east commons in progress.
30-Day Look Ahead:
- Interior stud wall framing on level 2 of building sector 1A is ongoing.
- MEP ceiling rough-in at building sector 1B and level 2 of building sector 1A is ongoing.
- MEPF hangers installation on level 2 of building sector 1B to be completed.
- Exterior brick around the perimeter of the building to be completed.
- Installation of exterior wall panels in building sectors 1A and 1B to continue.
- Installation of the site underground utilities is ongoing.
- Installation of TPO roofing at the east and west commons to be completed.
August 2022
Past Month’s Accomplishments:
- MEPF hangers, interior stud wall layout, and spraying of fireproofing at building sector 2B completed.
- Installation and pouring of concrete stair tread infills at stair 1 completed.
- Exterior wall panel installation at building sector 1A completed.
- Underground sanitary piping installation at parking lot area completed.
- Ceiling metal lath on level 2 of building sector 1B and building sector 2K completed.
- MEP above ceiling rough-in and exterior brick installation at building sector 1B completed.
- Building foundation wall waterproofing and backfill at building sector 1B in progress.
- MEPF hangers and interior wall layout on level 2 of building sector 1B in progress.
- Spraying of fireproofing ceiling lath on level 2 of building sectors 1A and 1B in progress.
- MEPF rough-in installation at building sector 1A Level 2, West Commons, and Gym in progress.
- Installation of TPO roof at West Commons in progress.
- Installation of exterior windows and interior door frames at building sector 1A in progress.
- Electrical in wall rough-in, installation of block retaining walls, and site underground sanitary piping in progress.
30-Day Look Ahead:
- Interior stud wall framing on level 2 of building sector 1A is ongoing.
- MEP ceiling rough-in on level 2 of building sector 1B is ongoing.
- Installation of exterior wall panels at building sector 1B is ongoing.
- Installation of site underground utilities to continue.
- Installation of TPO roof to continue.
- Installation of exterior windows, interior door frames, and electrical in wall rough-in is ongoing.
September 2022
Past Month’s Accomplishments:
- MEPF hangers installation and interior stud wall layout on level 2 of building sector 1A completed.
- Installation and pouring of concrete stair tread infills at stairs 2 and 3 completed.
- Spray fireproofing on level 2 of building sector 2B completed.
- Installation of exterior metal wall panels and MEP above ceiling rough-in in building sector 1B completed.
- Underground sanitary piping installation at the parking lot area completed.
- Installation of ceiling metal lath in building sector 2K completed.
- Installation of the grease interceptor completed.
- Electrical in wall rough-in, building foundation wall waterproofing, and backfill in building sector 1B in progress.
- MEPF hangers installation and interior wall layout on level 2 of building sector 1B in progress.
- Spray fireproofing ceiling lath in building sector 2K and on level 2 of building sector 1B in progress.
- MEPF rough-in in the west commons, gym, and on level 2 of building sector 1B in progress.
- Installation of TPO roofing at the connector in progress.
- Installation of exterior windows at building sector 1B and the gym in progress.
- Installation of interior door frames in building sector 1A in progress.
- Installation of block retaining walls and site underground storm piping in progress.
30-Day Look Ahead:
- Interior stud wall framing and MEP ceiling rough-in on level 2 of building sector 1B is ongoing.
- Installation of exterior wall panels on level 2 of building sectors 1A and 1B is ongoing.
- Installation of the site underground utilities to continue.
- Detailing of TPO roofing to continue.
- Installation of exterior windows and interior door frames is ongoing.
- MEP in-wall rough-in in building sectors 1A and 1B to continue.
October 2022
Past Month’s Accomplishments:
- Spray fireproofing, installation of exterior metal wall panels, and MEP rough-in at various levels of sector 2K completed.
- Underground sanitary piping installation at the south connector completed.
- Curb and gutter installation at the vehicular parking area completed.
- Drywall close-in on level 1 of sector 1A completed.
- Building foundation wall waterproofing and backfill at sector 1B completed.
30-Day Look Ahead:
- Interior stud wall framing in sectors 2K and 2G is ongoing.
- MEP ceiling and wall rough-ins in sectors 1A, 1B, and 2K to continue.
- Installation of the site underground utilities to continue.
- Detailing of TPO roof and installation of exterior windows and interior door frames are ongoing.
November 2022
Past Month’s Accomplishments:
- Installation of exterior metal wall panels and spray fireproofing in all other areas completed.
- Paving at the vehicular parking area 80% complete.
- MEP rough-in in sector 2B and drywall close-in on level 1 of sector 1B completed.
- Foundations for the main entrance canopy completed.
- Retaining wall at the southeast parking area and underground electrical duct bank completed.
30-Day Look Ahead:
- Interior stud wall framing and MEP ceiling rough-ins in sectors 2K and 2G to continue.
- Installation of the site underground utilities is ongoing.
- Installation of interior door frames, canopy steel structure, and TPO roofing to continue.
- MEP in wall rough-ins on level 2 of sector 1B is ongoing.
- Paining classrooms and all CMU walls in sectors 1A and 1B is ongoing.
December 2022
Past Month’s Accomplishments:
- MEP rough-ins in sector 2K completed.
- Drywall close-in on level 2 of sector 1A completed.
- Installation of the entrance canopy steel completed.
- Retaining wall at the northeast loading dock completed.
- Installation of the storm water detention system completed.
- Installation of the electrical switchgear completed.
- ACT ceiling grid on level 1 of sector 1A completed.
- Site underground water piping completed.
30-Day Look Ahead:
- Interior stud wall framing in sector 2G is ongoing.
- MEP ceiling rough-ins in sectors 2K and 2G are ongoing.
- Installation of the site underground utilities is ongoing.
- Installation of interior door frames is ongoing.
- Installation of the canopy steel structure and TPO roofing is ongoing.
- Painting of classrooms is sectors 1A and 1B and all CMU walls is ongoing.
- Installation of electrical generator and HVAC chiller to begin.