December 2022
Past Month’s Accomplishments:
- Prime and first coat painting of interior walls on levels 1 – 3 of sector 1A completed.
- ACT ceiling grid on level 1 of sector 1A completed.
- Fire sprinkler installation and electrical in wall rough-in on level 3 of sector 1B completed.
- Electrical in wall rough-ins, interior stud wall framing, and one-siding drywall on level 4 of sector 1B completed.
- Removal of unforeseen underground fuel tank completed.
- Drywall close in on levels 1 and 2 of sector 1B completed.
- Trim out of exterior metal panels, gutters, and downspouts at sectors 2G and 2K completed.
- Concrete curbs and gutters at lower parking lot completed.
- Water testing at exterior storefronts completed.
- Drywall close-in and finishing of interior walls on levels 2 and 3 of sector 1A in progress.
- Electrical in wall rough-ins on levels 3 and 4, as well as electrical power distribution rough-ins on levels 2 and 3 of sector 1B, are in progress.
- Telecom cabling installation on level 4 of sectors 1A and 1B in progress.
- Sprinkler installation in the gymnasium for sector 2G in progress.
- Elevator installation and MEP work for elevator shaft in progress.
- Stone base at the lower parking lot, as well as undercut and backfill of the bus loop area, are in progress.
- Underground water line tie-in at north side of site in progress.
30-Day Look Ahead:
- MEP, sprinkler, and telecom overhead rough-ins, testing, and insulation are ongoing.
- Base asphalt paving at the lower lot to begin.
- Rough-ins at main mechanical and electrical rooms are ongoing.
- One-siding walls at kitchen and performance rooms to begin.
- Prime paint and first coat at classrooms and corridors in sector 1B to begin.
- ACT ceiling grid installation at sector 1A tower is ongoing.
- Light fixture and ceiling device installation at sector 1A tower to begin.
November 2022
Past Month’s Accomplishments:
- Drywall one-siding interior walls on levels 2 and 3 of sector 1A completed.
- Fire sprinkler installation and electrical in wall rough-in in sector 1B completed. Telecom cabling installation on level 3 of sectors 1A and 1B completed.
- Electrical power distribution rough-in on levels 1 and 2 of sector 1A completed.
- Interior stud wall framing and one-siding drywall on level 4 of sector 1B completed.
- Interior door frame installation on levels 1 to 3 of sector 1A completed.
- Grading and undercutting and underground site utilities under parking lots completed.
- Underground gas utilities at north end of site completed.
- Interior paint at back of house spaces completed.
- RTU roof curbs completed.
30-Day Look Ahead:
- Trim out exterior metal panels and gutters and downspouts at sectors 2G and 2K in progress.
- Drywall close in, finishing interior walls, and interior door frame installation at sector 1A in progress.
- Fire sprinkler installation, electrical in wall rough-in, and electrical power distribution rough-ins at sector 1B in progress.
- Telecom cabling installation in sectors 1A and 1B in progress.
- Concrete curb and gutter at lower parking lot in progress.
- Elevator installation in progress.
- MEP, sprinkler, and telecom overhead rough-ins, testing, and insulation are ongoing.
- Base asphalt paving at the lower lot to begin.
- Rough-ins at the main mechanical and electrical rooms are ongoing.
- Water testing of exterior window units to be completed.
- One-siding walls at the kitchen and performance rooms to begin.
- Prime paint and first coat at classrooms and corridors in sector 1A to begin.
- ACT ceiling grid installation at the sector 1A tower to begin.
October 2022
Past Month’s Accomplishments:
- Exterior metal panel installation at sectors 1B and 2G completed.
- Underground sanitary tie in at Oliver Street completed.
- Entrance canopy AVB completed.
- Exterior window installation and caulking, as well as metal ceiling lath installation at sector 2G, are completed.
- In-wall MEP rough-ins on various levels of sector 1A completed.
- Installation of underground grease interceptor at north site completed.
- Trim out of exterior metal panels, gutters, and downspouts for sectors 2G and 2K in progress.
- Drywall one-siding interior walls, interior door frame installation, and electrical power distribution rough-ins for sector 1A in progress.
- Fire sprinkler installation, electrical in wall rough-ins, interior stud wall framing, and one-siding drywall for sector 1B in progress.
- Telecom cabling installation for sectors 1A and 1B in progress.
- Grading and undercutting of the lower parking lot in progress.
- Underground site utilities and gas utilities throughout the site in progress.
30-Day Look Ahead:
- MEP, sprinkler, and telecom overhead rough-in, testing, and insulation are ongoing.
- Interior paint at back of house spaces to begin.
- Curb and gutter construction, as well as base asphalt paving at lower lot, are to begin.
- Mechanical and electrical room rough-ins to begin.
September 2022
Past Month’s Accomplishments:
- Exterior metal panel and interior CMU block wall bracing installation at building sector 2G completed.
- Primary duct bank installation at north side of site completed.
- Entrance canopy framing and blocking completed.
- Window installation and caulking at building sector 1A completed.
- In-wall rough-in on level 1 of building sector 1A completed.
- Drywall framing and top out in the kitchen of building sector 2K completed.
- Spray fireproofing on level 4 and stair 1 installation at the tower of building sector 1B completed.
- TPO roofing installation at connector roofs completed.
- One-siding drywall, sprinkler installation, electrical in wall rough-in, interior stud wall framing, and electrical power distribution on various level for building sector 1A in progress.
- Installation of exterior metal wall panels at building sector 1B in progress.
- Telecom cabling installation for building sectors 1A and 1B in progress.
- Sanitary tie-in at north side of site in progress.
- Grading of lower parking lot in progress.
30-Day Look Ahead:
- MEP, sprinkler, and telecom overhead rough-in testing and insulation is ongoing.
- Installation of exterior metal panels to be completed.
- Exterior window installation at building sectors 1B and 2G to begin.
- Grading of bus loop and lower lot to begin.
- Gas tie-in at north end of site to begin.
- Wall close-ins and interior door frame installation at level 1 of building sector 1A to begin.
August 2022
Past Month’s Accomplishments:
- Building perimeter knee wall construction at building sector 2G completed.
- Trim out and flashing exterior metal wall panels at building sectors 1A and 2K completed.
- Electrical overhead rough-in for level 1 of building sector 1A completed.
- Interior stud wall framing and drywall top out at level 3 of building sector 1A and levels 1 and 2 of building sector 1B completed.
- Spraying of fireproofing at levels 2 and 3 of building sector 1B completed.
- Installation of MEP ceiling hangers and overhead rough-in at level 1 of building sector 1B completed.
- Roof parapet framing and blocking completed.
- Stair 2 installation in building sector 1A tower completed.
- Secondary steel installation and perimeter knee wall construction at building sector 1B in progress.
- Exterior metal wall panels and interior CMU block wall bracing installation for building at sector 2G in progress.
- Sprinkler installation at level 1 and electrical overhead rough-in for levels 1 - 3 of building sector 1A in progress.
- Interior stud wall framing and one-siding drywall on levels 1- 3 of building sector 1B in progress.
- Spraying of fireproofing on level 4 and window installation at all levels of building sector 1A in progress.
- Installation of MEP ceiling hangers and interior stud wall framing on level 1 of building sector 1B in progress.
- Site underground stormwater and water line utilities at the south side of the building are in progress.
- Stair 1 installation at building sector 1B tower in progress.
- Grading of lower parking lot at SW corner of site in progress.
30-Day Look Ahead:
- Exterior metal wall panel installation at building sector 1B to begin.
- MEP overhead rough-in, testing, and insulation is ongoing.
- Sprinkler installation at building sector 1A tower in ongoing.
- Overhead HVAC ductwork installation at building sector 1A and 1B is ongoing.
- Spraying of fireproofing at level 4 of building sectors 1Aand 1B to continue.
- TPO roofing installation at building sector 1 and 2 connectors to continue.
- Secondary steel installation at building sector 1B tower to continue.
- Interior door frame Installation at level 1 of building sector 1A to begin.
- Exterior window installation at building sectors 2K and 2G to begin.
July 2022
Past Month’s Accomplishments:
- Elevator shaft top out at building sector 1B completed.
- HVAC ductwork risers in building sector 1A tower completed.
- Installation and pouring of concrete stair tread infills at the stair 3 egress in building sector 1A completed.
- Spraying of fireproofing on the 3rd floor of building sector 1A completed.
- Exterior metal wall panel installation at building sectors 1A and 2G completed.
- Roof parapet framing and blocking at building sector 1A completed.
- Ceiling hat channel installation at building sector 2K completed.
- Secondary steel installation at building sectors 1B and 2G in progress.
- Building perimeter knee wall construction and installation of exterior metal wall panels at building sector 2G in progress.
- Sprinkler installation and electrical overhead rough-in on 1st floor of building sector 1A in progress.
- Interior wall framing and one-siding drywall on floors 1 and 2 of building sector 1A in progress.
- Spraying of fireproofing on floor 2 of building sector 1B in progress.
- Installation of MEP ceiling hangers and interior stud wall framing floor 1 of building sector 1B in progress.
- Stair 2 installation at building sector 1A tower in progress.
- Site underground stormwater and water line utilities at the south side of a building in progress.
- Interior CMU block wall bracing installation at building sector 2G in progress.
- Roof parapet framing and blocking in progress.
30-Day Look Ahead:
- Exterior metal wall panel installation at building sector 2G to begin.
- MEP overhead rough-in, testing, and insulation is ongoing.
- Sprinkler installation at Sector 1A tower is ongoing.
- Overhead HVAC ductwork installation at building sectors 1A and 1B towers is ongoing.
- Spraying of fireproofing at building sector 1B to continue.
- TPO roofing installation at building sector 1A is ongoing.
- Secondary steel installation at building sector 1B tower is ongoing.
June 2022
Past Month’s Accomplishments:
- Interior CMU block walls and ceiling hat channel installation for fireproofing at sector 2K completed.
- All concrete slab pours on metal deck floors at sector 1B completed.
- Steel for entrance canopy completed.
- Fireproofing at first and second floors of building sector 1A completed.
- Metal panel roof at building sector 2G completed.
- Underground telecom duct bank installation at west side of site completed.
- Secondary steel install at building sectors 1B, 2G, and 2K in progress.
- Building perimeter knee wall construction at building sectors 2G and 2K in progress.
- Building foundation wall waterproofing and backfill in progress.
- MEPF hangers and interior wall construction at building sector 1A for the first, second, and third floors in progress.
- Interior wall framing and one-siding at sector 1A for the first and second floors in progress.
- Spray fireproofing at building sector 1A on the third floor and 1B on the first floor in progress.
- Storm water utilities at south side of building in progress.
- Installation of stair 3 in progress.
- CMU bracing installation at building sector 2G in progress.
- Roof parapet framing and blocking in progress.
30-Day Look Ahead:
- Exterior metal wall panel installation at building sector 2K to begin.
- MEPF hanger installation at building sectors 1A and 1B is ongoing.
- Installation of HVAC ductwork at building sector 1A on the second and third floors to continue.
- Installation of interior metal stairs at Stair 2 to begin.
- Fireproofing at 1B sector to continue.
- TPO roof installation to begin.
May 2022
Past Month’s Accomplishments:
- Interior CMU block walls at stage completed.
- Concrete pouring of stage and stairs at gym completed.
- Primary steel erection at building sector 1B completed.
- Building perimeter knee wall construction and secondary steel installation at building sector 1A completed.
- Metal panel roof at building sector 2K completed.
- Secondary steel installation and building perimeter knee wall construction at building sector 2K is in progress.
- Installation of interior hat channel and MEPF hangers at building sector 2K in progress.
- Building foundation wall waterproofing and backfill in progress.
- MEPF Hangers, interior wall construction, and fireproofing at building sector 1A in progress.
- Stormwater utilities at SW corner in progress.
30-Day Look Ahead:
- Exterior metal wall panel installation at building sector 1A to begin.
- MEPF hanger installation, interior wall framing, and one-siding with drywall in building sector 1A is ongoing.
- Installation of HVAC ductwork on first floor of building sector 1A to begin.
- Installation of interior metal stairs to begin.
- CMU bracing installation at building sector 2G is ongoing.
- Underground telecom ductbank installation at west side of site is ongoing.
- Roof parapet framing and blocking to continue.
- Concrete slab on metal deck pours on the second, third, and fourth floors in sector 1B to continue.
April 2022
Past Month’s Accomplishments:
- Pouring of elevated concrete deck in sector 1A on the third and fourth floors completed.
- Primary steel erection at sectors 2G and 2K completed.
- Interior CMU block elevator shaft walls completed.
- Grading of turf field area completed.
- Secondary steel installation at sector 1A in progress.
- Primary steel erection for sector 1B in progress.
- Building perimeter knee wall framing and sheathing at sector 1A in progress.
- Building foundation wall waterproofing and backfill in progress.
30-Day Look Ahead:
- Exterior metal panel deliveries to begin.
- Metal panel roof installation at sectors 2G and 2K is ongoing.
- Exterior metal wall panel installation to begin.
- MEPF hanger installation at sector 1A to continue.
- Interior wall framing and one-siding with drywall at sector 1A is ongoing.
- Installation of stormwater utilities at SW corner to begin.
March 2022
Past Month’s Accomplishments:
- Pouring of sector 1A concrete slab on second floor metal deck completed.
- Steel detailing and secondary steel installation at sector 1A in progress.
- Primary steel erection at 2K in progress.
- MEP slab rough-in at the sector 1A elevated decks in progress.
- CMU walls in sector 2G and CMU elevator shaft in progress.
- Grading turf field in progress.
- Foundation wall damp-roofing and backfill in progress.
30-Day Look Ahead:
- Building perimeter knee wall framing and AVB at sector 1A is ongoing.
- Roof parapet framing at sector 1A is ongoing.
- MEP Hangers and Interior Wall Layout at sector 1A to begin.
- Structural steel erection in sectors 2K, 2G, and 1B to continue.
- Façade metal panel deliveries to begin.
- Concrete slab on deck pours at sector 1A on the third and fourth floor to continue.
February 2022
Past Month’s Accomplishments:
- Pouring concrete building foundations at building sector 1B completed.
- Rough in under slab MEP utilities at building sector 1B completed.
- Concrete slab on grade pours at sector 2G and 2K completed.
- Concrete slab on grade preparation at sector 1B in progress.
- Structural steel erection in sector 1A in progress.
- CMU walls in sector 2G in progress.
30-Day Look Ahead:
- Concrete slab on deck pours in sector 1A are ongoing.
- Structural steel erection in sectors 2K and 2G are ongoing.
- Exterior framing and sheathing to begin.
January 2022
Past Month’s Accomplishments:
- Sorting and hauling of existing building demolition debris complete.
- Pouring of concrete foundations at building sectors 2K, 2G, and 1A complete.
- Concrete slab on grade pours at sector 1A complete.
- Pouring of concrete building foundation footings, piers and walls at sector 1B in progress.
- Construction of site access roads and laydown areas underway.
- Installation of under slab utilities at building sectors 2G and 1B in progress.
- Structural steel deliveries in progress.
30-Day Look Ahead:
- Concrete slab on grade pours at sectors 2G and 2K to continue.
- Under slab utilities at sector 1B to continue.
- Structural steel erection to begin.