Hyattsville Middle School

Status
Complete
Funding Model
P3
Project Type
Replacement
Budget
$72,000,000
Architect
Stantec
General Contractor
Gilbane Building Co.
Project Manager
Brailsford & Dunlavey

School Information

Principal
Chanita Stamper
Address
6001 42nd Ave, Hyattsville, MD 20781
Neighborhood
Hyattsville, West Riverdale, University Park
School Board District
District 3
County Council District
District 2
State Legislative District
District 22

Project Timeline

Blueprint Project Timeline.png

Project Scope

Construction of a new 161,785 SF school with a capacity of 1,200 students on the existing Hyattsville Middle School site.

News & Announcements

There are currently no announcements for this project.

Project Updates

Year 2023

August 2023 

Past Month’s Accomplishments: 

  • Site inspections completed. 
  • ADA inspections completed 
  • Electrical inspection completed. 
  • DoH inspection completed. 
  • Building inspection completed 
  • Stage and Performance Room curtains completed. 
  • Performance Room mirrors completed. 
  • Divider walls in Band and Orchestra Rooms completed. 
  • Punch list in progress. 
  • Owner training in progress. 

30-Day Look Ahead:  

  • Punch list is ongoing. 
  • Owner training is ongoing. 

July 2023 

Past Month’s Accomplishments: 

  • Ceiling close ins at remaining drop ceilings for Sector 2 completed. 
  • Lighting installation at baffle ceiling Learning Stair connector for Sector 2 completed. 
  • Rough cleaning and final painting at Kitchen for Sector 2 completed. 
  • Furniture installation at 1st floor classrooms and 4th floor classrooms for Sector 1 completed. 
  • Flooring installation at Learning Stair connector for Sector 2 completed. 
  • Wall protection installation at Sector 2 common areas completed. 
  • Wood flooring installation at Dance Room and Sanding / Sealing Gym for Sector 2 completed. 
  • Building signage installation at Sector 1 completed. 
  • Installation for building graphics at Sector 1 and 2 completed. 
  • Gym sealing and striping completed. 
  • Wood paneling installation at Media 1 / 2 for Sector 1 completed. 
  • Site perimeter fencing around entire site completed. 
  • Biopond installation at SW corner completed. 
  • Planting installation and seeding completed. 
  • Parking Lot Top Coats and Striping completed. 
  • Site furnishings installation at plazas and field areas completed. 
  • Sidewalk replacement at west site and staircase completed. 
  • PGCPS Punch List at Classrooms (2, 3, 4 ) completed. 
  • Elevator final inspection completed. 
  • Sprinkler Final inspection completed. 
  • Ansul System Final Testing completed. 
  • Flooring installation at Learning Stair in progress. 
  • Furniture Unpacking and Staging for All Areas in progress. 
  • Installation for toilet accessories at Sector 1 and 2 in progress. 
  • Accent panel painting in progress. 
  • Site furnishings installation at plazas and field areas in progress. 
  • Monument sign installation in progress. 
  • Punch List throughout building in progress. 

30-Day Look Ahead:  

  • Commissioning MEP systems is ongoing. 
  • Completion of balance for exterior painting is ongoing. 
  • Completion of remaining inspections is ongoing. 
  • PGCPS punch list for remaining areas to begin. 

June 2023 

Past Month’s Accomplishments: 

  • Flooring at 1st Floor Sector 1 Classroom Tower completed. 
  • Drop of all ceiling tiles at Sector 1 Classroom Tower completed. 
  • Drop of ceiling tile at Dance Room & Kitchen Sector 2 completed. 
  • Ceiling grid and devices at remaining drop ceiling locations for Sector 2 completed. 
  • Wood flooring subbase and planking at Gymnasium for Sector 2 completed. 
  • Wall protection in Classroom Tower corridors & stairs for Sector 2 completed. 
  • Furniture installation at Floors 2 and 3 Classrooms for Sector 1 completed. 
  • Toilet partition installation for second and third floor bathrooms at Sector 1 completed. 
  • Baffle ceiling installation at Learning Stair connector for Sector 2 completed. 
  • Collaboration Space ceilings and light fixtures for Classroom Tower completed. 
  • Flooring in Dining space for Sector 2 completed. 
  • Wall and floor tile, lockers, fixtures, light installation in Locker Rooms completed. 
  • Paving bus loop and adjacent sidewalks completed. 
  • Biopond installation and plantings at west and east bioponds completed. 
  • Field installation and perimeter fencing for Turf Field completed. 
  • TPO Roof coping completed. 
  • Permanent chiller set and start up completed. 
  • Base paved Service Entrance lot completed. 
  • Entrance canopy lighting and façade panels completed. 
  • Ceiling close ins at remaining drop ceilings for Sector 2 in progress. 
  • Lighting installation at baffle ceiling Learning Stair connector for Sector 2 in progress. 
  • Rough cleaning and final painting at Kitchen for Sector 2 in progress. 
  • Furniture installation at 1st floor classrooms and 4th floor classrooms for Sector 1 in progress. 
  • Flooring installation at Learning Stair connector for Sector 2 in progress. 
  • Wall protection installation at Sector 2 common areas in progress. 
  • Wood flooring installation at Dance Room and Sanding / Sealing Gym for Sector 2 in progress. 
  • Building signage installation for Sector 1 in progress. 
  • Wood paneling installation at Media 1 / 2 for Sector 1 in progress. 
  • Install toilet partitions and accessories for Sector 1 and 2 in progress. 
  • Site fencing at north site in progress. 
  • Biopond installation at SW corner in progress. 
  • Planting installation and seeding in progress. 
  • Accent panel painting in progress. 
  • Site furnishings installation at plazas and field areas in progress. 
  • Sidewalk replacement at west site and staircase in progress. 
  • Monument sign installation in progress. 

30-Day Look Ahead:  

  • Wood flooring sanding and sealing (Dance, Gym, Stage) to start. 
  • Remaining ceiling tile drop in Sector 2 to be completed. 
  • AV, IT, Security systems testing to start. 
  • TAB and Cx MEP Systems ongoing. 
  • Elevator final testing and inspections to start. 
  • DoH Kitchen inspections to start. 
  • Electrical preliminary finals at Classroom Tower ongoing. 
  • Mill and overlay Oliver Street to start. 
  • Final paving and striping parking lots to start. 
  • Furniture installation in Sector 2 Performance Rooms & Dining to start. 
  • PGCPS punch list Classrooms 2, 3, 4 to start. 

May 2023 

Past Month’s Accomplishments: 

  • Drywall close-in and finishing interior walls at the dining area completed. 
  • Full building sprinkler system fire pump test completed. 
  • Tile installations on the 4th floor bathrooms completed. 
  • VCT flooring on the 1st Floor classroom tower completed. 
  • Learning stair wall close-ins and finishing completed. 
  • Locker installation in the classroom tower completed. 
  • Ceiling grid and fixture installations, as well as devices in the media center (1/2 and 3/4) completed. 
  • Painting walls in the media center (1/2 and 3/4) completed. 
  • Skylight installation at media (3/4) and dining completed. 
  • Rough grading on the east and south sides of the site completed. 
  • Equipment start ups (boilers, generator, temp chiller, and all RTUs) completed. 
  • Concrete curb and gutter for the bus loop completed. 
  • Remainder of the base pave at the parking lot completed. 
  • Base pave bus loop completed. 
  • Biopond installation on the west side of the building completed. 

30-Day Look Ahead: 

  • Wood flooring installation in Gym to begin. 
  • Remaining ceiling tile installation in classroom tower to conclude. 
  • Ceiling grid in Performance Rooms to begin. 
  • Toilet partitions and accessories installation to begin. 
  • Mill and overlay of Oliver Street to begin. 
  • Setting exterior furnishing to begin. 
  • Landscaping and fencing at west and north site to begin. 
  • Monument Sign installation to begin. 
  • Furniture installation in classroom tower to begin. 
  • PGCPS punch list in classrooms 2, 3, and 4 to begin. 

April 2023 

Past Month’s Accomplishments: 

  • Drywall close-in and finishing interior walls at Stair 1 completed. 
  • Telecom cabling terminations at Sector 2A/2B on the third and fourth floor are completed. 
  • Permanent power and energizing classroom tower on all floors completed.  
  • Sprinkler hydro testing (2K and Stage area) completed. 
  • Bulkhead close ins for fourth floor and sector 2G bathrooms completed. 
  • Tile installation on fourth floor bathrooms completed. 
  • VCT flooring for second, third, and fourth floors completed. 
  • Learning Stair fireproofing and wall framing completed. 
  • Autex panels and basketball hoops in gymnasium completed. 
  • Ceiling grid and quarry tile installation in kitchen completed. 
  • Finishing walls in Media Center (1/2 & 3 /4) completed. 
  • Ceiling grid and devices at Media 1 / 2 completed. 
  • Rough grading at north side of site completed. 
  • Setting RTUs 2, 4, 5, 7, 9 at roof levels completed. 
  • Curb and gutter for Oliver Street Road widening completed. 
  • Seeding and tree planting at west side of parking lot completed. 

30-Day Look Ahead: 

  • Kitchen equipment installation to begin. 
  • Locker installation in Classroom Tower to begin. 
  • Start up RTUs to begin. 
  • HVA controls programming to begin. 
  • Acclimation for gym wood flooring to begin. 
  • IT device install and labeling to begin. 
  • VCT Flooring installation at 1A Tower to begin. 
  • Ceramic tile installation at locker rooms to begin.  
  • Sidewalks at south and north sides of building to begin. 
  • Grading at bus loop to begin. 

March 2023 

Past Month’s Accomplishments: 

  • Drywall close-in and finishing interior walls at Stair 3 completed. 
  • Drywall close-in and finishing interior walls in gymnasium completed. 
  • Telecom cabling terminations for Sector 2A/2B on the second floor completed. 
  • Electrical switchgear setting and main feeder pulling completed. 
  • Sprinkler hydro testing for the third and fourth floors completed. 
  • Bulkhead close-ins for the first, second, and third floors and bathrooms completed. 
  • Tile installation for the second and third floor bathrooms completed. 
  • Learning stair steel and concrete in the dining area completed. 
  • Overhead painting in gym completed. 
  • Set kitchen hood and exhaust duct completed. 
  • Hanging walls in Media Center (1 / 2 and 3 /4) completed. 
  • Rough grading at the west side of the site completed. 
  • Setting RTUs (1, 3, 6, and 9) at roof levels completed. 

30-Day Look Ahead: 

  • MEP flushing and systems testing to continue. 
  • Quarry tile in Kitchen to begin. 
  • Receive wood flooring for Gym to begin. 
  • Devices and labeling to continue. 
  • VCT Flooring installation at 1A Tower to continue. 
  • Ceramic tile installation at Locker Rooms to begin. 
  • Fire alarm testing to begin. 
  • Set last batch of RTUs to begin. 
  • Sidewalks at west and north sides of building to begin. 

February 2023 

Past Month’s Accomplishments: 

  • Prime and First Coat paint interior for walls at Sectors 3B, 4A, and 4B completed. 
  • ACT Ceiling Grid at Sector 1B, 2B, 3B, and 4A completed. 
  • Fire sprinkler installation at Stairs and Dining Commons completed. 
  • Drywall close in for fourth floor completed. 
  • Drywall close in at Kitchen completed. 
  • Drywall close in for Media Floors (1/2) completed. 
  • Electrical in wall rough-in for Performance Rooms and Gym completed. 
  • Ceiling devices, GRDs and light fixture installations for 3A, 1B, 2B completed. 
  • Sprinkler hydro testing for the first floor completed. 
  • Elevator temp use inspection completed. 
  • Underground water line testing and flushing at north side of site completed. 

30-Day Look Ahead: 

  • Drywall close in and interior walls finish at Stair 3 to begin. 
  • Drywall close in and interior walls finish in Gymnasium to begin. 
  • Telecom cabling terminations for Sector 2A/2B on the second floor to begin. 
  • Fire Alarm wiring for third and fourth floor to begin. 
  • Setting electrical switchgear and pulling main feeders for all areas to begin. 
  • Sprinkler hydro testing for second floor to begin. 
  • Tile installation for second floor bathrooms to begin. 
  • Learning Stair installation in Dining Area to begin. 
  • Setting casework in Classrooms to begin. 
  • MEP flushing and systems testing ongoing. 
  • Set Kitchen Hood and Ceiling Tile in Kitchen to start. 
  • Complete overhead work in Gym for Painting to start. 
  • Interior glazing installation at Classroom Tower is ongoing. 
  • VCT Flooring installation at 1A Tower is ongoing. 
  • Ceramic tile installation for 1A/1B bathrooms is ongoing. 
  • Setting the first batch of RTUs to begin. 

January 2023 

Past Month’s Accomplishments: 

  • Prime and first coat painting of interior walls on levels 1 and 2 of sector 1B completed. 
  • ACT ceiling grid on levels 2 and 3 of sector 1A completed. 
  • Fire sprinkler installation on level 4 of sector 1B completed. 
  • Drywall close-in on level 3 of sector 1B completed. 
  • Electrical in-wall rough-in on levels 3 and 4 of sector 1B completed. 
  • Installation of ceiling devices, GRDs, and light fixtures for sector 1A and 2A academic classrooms completed. 
  • Telecom cabling terminations on level 1 of sectors 1A and 1B in progress. 
  • Electrical power distribution rough-in on levels 3 and 4 of sector 1B in progress. 
  • Sprinkler installation at the gymnasium in sector 2G in progress. 
  • Drywall close-in and finishing of interior walls on levels 2 and 3 of sector 1A in progress. 

30-Day Look Ahead: 

  • MEP, sprinkler, and telecom overhead rough-in, testing, and insulation is ongoing. 
  • Base asphalt paving at the lower lot to continue. 
  • Setting of the Pepco transformer and switchgear to begin. 
  • One-siding of walls in the kitchen and performance rooms to begin. 
  • Prime and first coat painting for the classrooms and corridors in sector 3B to begin. 
  • ACT ceiling grid installation at the sector 1B tower is ongoing. 
  • Light fixture and ceiling device installation at the sector 3A tower to begin. 
  • VCT flooring installation at sector 1A to begin. 
  • Learning Stair installation to begin. 

Year 2022

December 2022 

Past Month’s Accomplishments: 

  • Prime and first coat painting of interior walls on levels 1 – 3 of sector 1A completed. 
  • ACT ceiling grid on level 1 of sector 1A completed. 
  • Fire sprinkler installation and electrical in wall rough-in on level 3 of sector 1B completed. 
  • Electrical in wall rough-ins, interior stud wall framing, and one-siding drywall on level 4 of sector 1B completed. 
  • Removal of unforeseen underground fuel tank completed. 
  • Drywall close in on levels 1 and 2 of sector 1B completed. 
  • Trim out of exterior metal panels, gutters, and downspouts at sectors 2G and 2K completed. 
  • Concrete curbs and gutters at lower parking lot completed. 
  • Water testing at exterior storefronts completed. 
  • Drywall close-in and finishing of interior walls on levels 2 and 3 of sector 1A in progress. 
  • Electrical in wall rough-ins on levels 3 and 4, as well as electrical power distribution rough-ins on levels 2 and 3 of sector 1B, are in progress. 
  • Telecom cabling installation on level 4 of sectors 1A and 1B in progress. 
  • Sprinkler installation in the gymnasium for sector 2G in progress. 
  • Elevator installation and MEP work for elevator shaft in progress. 
  • Stone base at the lower parking lot, as well as undercut and backfill of the bus loop area, are in progress. 
  • Underground water line tie-in at north side of site in progress. 

30-Day Look Ahead: 

  • MEP, sprinkler, and telecom overhead rough-ins, testing, and insulation are ongoing. 
  • Base asphalt paving at the lower lot to begin. 
  • Rough-ins at main mechanical and electrical rooms are ongoing. 
  • One-siding walls at kitchen and performance rooms to begin. 
  • Prime paint and first coat at classrooms and corridors in sector 1B to begin. 
  • ACT ceiling grid installation at sector 1A tower is ongoing. 
  • Light fixture and ceiling device installation at sector 1A tower to begin. 

November 2022 

Past Month’s Accomplishments: 

  • Drywall one-siding interior walls on levels 2 and 3 of sector 1A completed. 
  • Fire sprinkler installation and electrical in wall rough-in in sector 1B completed. Telecom cabling installation on level 3 of sectors 1A and 1B completed. 
  • Electrical power distribution rough-in on levels 1 and 2 of sector 1A completed. 
  • Interior stud wall framing and one-siding drywall on level 4 of sector 1B completed. 
  • Interior door frame installation on levels 1 to 3 of sector 1A completed. 
  • Grading and undercutting and underground site utilities under parking lots completed. 
  • Underground gas utilities at north end of site completed. 
  • Interior paint at back of house spaces completed. 
  • RTU roof curbs completed. 

30-Day Look Ahead: 

  • Trim out exterior metal panels and gutters and downspouts at sectors 2G and 2K in progress. 
  • Drywall close in, finishing interior walls, and interior door frame installation at sector 1A in progress. 
  • Fire sprinkler installation, electrical in wall rough-in, and electrical power distribution rough-ins at sector 1B in progress. 
  • Telecom cabling installation in sectors 1A and 1B in progress. 
  • Concrete curb and gutter at lower parking lot in progress. 
  • Elevator installation in progress. 
  • MEP, sprinkler, and telecom overhead rough-ins, testing, and insulation are ongoing. 
  • Base asphalt paving at the lower lot to begin. 
  • Rough-ins at the main mechanical and electrical rooms are ongoing. 
  • Water testing of exterior window units to be completed. 
  • One-siding walls at the kitchen and performance rooms to begin. 
  • Prime paint and first coat at classrooms and corridors in sector 1A to begin. 
  • ACT ceiling grid installation at the sector 1A tower to begin. 

October 2022 

Past Month’s Accomplishments: 

  • Exterior metal panel installation at sectors 1B and 2G completed. 
  • Underground sanitary tie in at Oliver Street completed. 
  • Entrance canopy AVB completed. 
  • Exterior window installation and caulking, as well as metal ceiling lath installation at sector 2G, are completed. 
  • In-wall MEP rough-ins on various levels of sector 1A completed. 
  • Installation of underground grease interceptor at north site completed. 
  • Trim out of exterior metal panels, gutters, and downspouts for sectors 2G and 2K in progress. 
  • Drywall one-siding interior walls, interior door frame installation, and electrical power distribution rough-ins for sector 1A in progress. 
  • Fire sprinkler installation, electrical in wall rough-ins, interior stud wall framing, and one-siding drywall for sector 1B in progress. 
  • Telecom cabling installation for sectors 1A and 1B in progress. 
  • Grading and undercutting of the lower parking lot in progress. 
  • Underground site utilities and gas utilities throughout the site in progress. 

30-Day Look Ahead: 

  • MEP, sprinkler, and telecom overhead rough-in, testing, and insulation are ongoing. 
  • Interior paint at back of house spaces to begin. 
  • Curb and gutter construction, as well as base asphalt paving at lower lot, are to begin. 
  • Mechanical and electrical room rough-ins to begin. 

September 2022 

Past Month’s Accomplishments: 

  • Exterior metal panel and interior CMU block wall bracing installation at building sector 2G completed. 
  • Primary duct bank installation at north side of site completed. 
  • Entrance canopy framing and blocking completed. 
  • Window installation and caulking at building sector 1A completed. 
  • In-wall rough-in on level 1 of building sector 1A completed.
  • Drywall framing and top out in the kitchen of building sector 2K completed. 
  • Spray fireproofing on level 4 and stair 1 installation at the tower of building sector 1B completed. 
  • TPO roofing installation at connector roofs completed. 
  • One-siding drywall, sprinkler installation, electrical in wall rough-in, interior stud wall framing, and electrical power distribution on various level for building sector 1A in progress. 
  • Installation of exterior metal wall panels at building sector 1B in progress. 
  • Telecom cabling installation for building sectors 1A and 1B in progress. 
  • Sanitary tie-in at north side of site in progress. 
  • Grading of lower parking lot in progress. 

30-Day Look Ahead: 

  • MEP, sprinkler, and telecom overhead rough-in testing and insulation is ongoing. 
  • Installation of exterior metal panels to be completed. 
  • Exterior window installation at building sectors 1B and 2G to begin. 
  • Grading of bus loop and lower lot to begin. 
  • Gas tie-in at north end of site to begin. 
  • Wall close-ins and interior door frame installation at level 1 of building sector 1A to begin. 

August 2022 

Past Month’s Accomplishments: 

  • Building perimeter knee wall construction at building sector 2G completed. 
  • Trim out and flashing exterior metal wall panels at building sectors 1A and 2K completed. 
  • Electrical overhead rough-in for level 1 of building sector 1A completed. 
  • Interior stud wall framing and drywall top out at level 3 of building sector 1A and levels 1 and 2 of building sector 1B completed. 
  • Spraying of fireproofing at levels 2 and 3 of building sector 1B completed. 
  • Installation of MEP ceiling hangers and overhead rough-in at level 1 of building sector 1B completed. 
  • Roof parapet framing and blocking completed. 
  • Stair 2 installation in building sector 1A tower completed. 
  • Secondary steel installation and perimeter knee wall construction at building sector 1B in progress. 
  • Exterior metal wall panels and interior CMU block wall bracing installation for building at sector 2G in progress. 
  • Sprinkler installation at level 1 and electrical overhead rough-in for levels 1 - 3 of building sector 1A in progress. 
  • Interior stud wall framing and one-siding drywall on levels 1- 3 of building sector 1B in progress. 
  • Spraying of fireproofing on level 4 and window installation at all levels of building sector 1A in progress. 
  • Installation of MEP ceiling hangers and interior stud wall framing on level 1 of building sector 1B in progress. 
  • Site underground stormwater and water line utilities at the south side of the building are in progress. 
  • Stair 1 installation at building sector 1B tower in progress. 
  • Grading of lower parking lot at SW corner of site in progress. 

30-Day Look Ahead: 

  • Exterior metal wall panel installation at building sector 1B to begin. 
  • MEP overhead rough-in, testing, and insulation is ongoing. 
  • Sprinkler installation at building sector 1A tower in ongoing. 
  • Overhead HVAC ductwork installation at building sector 1A and 1B is ongoing. 
  • Spraying of fireproofing at level 4 of building sectors 1Aand 1B to continue. 
  • TPO roofing installation at building sector 1 and 2 connectors to continue. 
  • Secondary steel installation at building sector 1B tower to continue. 
  • Interior door frame Installation at level 1 of building sector 1A to begin. 
  • Exterior window installation at building sectors 2K and 2G to begin. 

July 2022 

Past Month’s Accomplishments: 

  • Elevator shaft top out at building sector 1B completed. 
  • HVAC ductwork risers in building sector 1A tower completed. 
  • Installation and pouring of concrete stair tread infills at the stair 3 egress in building sector 1A completed. 
  • Spraying of fireproofing on the 3rd floor of building sector 1A completed. 
  • Exterior metal wall panel installation at building sectors 1A and 2G completed. 
  • Roof parapet framing and blocking at building sector 1A completed. 
  • Ceiling hat channel installation at building sector 2K completed. 
  • Secondary steel installation at building sectors 1B and 2G in progress. 
  • Building perimeter knee wall construction and installation of exterior metal wall panels at building sector 2G in progress. 
  • Sprinkler installation and electrical overhead rough-in on 1st floor of building sector 1A in progress. 
  • Interior wall framing and one-siding drywall on floors 1 and 2 of building sector 1A in progress. 
  • Spraying of fireproofing on floor 2 of building sector 1B in progress. 
  • Installation of MEP ceiling hangers and interior stud wall framing floor 1 of building sector 1B in progress. 
  • Stair 2 installation at building sector 1A tower in progress. 
  • Site underground stormwater and water line utilities at the south side of a building in progress. 
  • Interior CMU block wall bracing installation at building sector 2G in progress. 
  • Roof parapet framing and blocking in progress. 

30-Day Look Ahead: 

  • Exterior metal wall panel installation at building sector 2G to begin. 
  • MEP overhead rough-in, testing, and insulation is ongoing. 
  • Sprinkler installation at Sector 1A tower is ongoing. 
  • Overhead HVAC ductwork installation at building sectors 1A and 1B towers is ongoing. 
  • Spraying of fireproofing at building sector 1B to continue. 
  • TPO roofing installation at building sector 1A is ongoing. 
  • Secondary steel installation at building sector 1B tower is ongoing. 

June 2022 

Past Month’s Accomplishments: 

  • Interior CMU block walls and ceiling hat channel installation for fireproofing at sector 2K completed. 
  • All concrete slab pours on metal deck floors at sector 1B completed. 
  • Steel for entrance canopy completed. 
  • Fireproofing at first and second floors of building sector 1A completed. 
  • Metal panel roof at building sector 2G completed. 
  • Underground telecom duct bank installation at west side of site completed. 
  • Secondary steel install at building sectors 1B, 2G, and 2K in progress. 
  • Building perimeter knee wall construction at building sectors 2G and 2K in progress. 
  • Building foundation wall waterproofing and backfill in progress. 
  • MEPF hangers and interior wall construction at building sector 1A for the first, second, and third floors in progress. 
  • Interior wall framing and one-siding at sector 1A for the first and second floors in progress. 
  • Spray fireproofing at building sector 1A on the third floor and 1B on the first floor in progress. 
  • Storm water utilities at south side of building in progress. 
  • Installation of stair 3 in progress. 
  • CMU bracing installation at building sector 2G in progress. 
  • Roof parapet framing and blocking in progress. 

30-Day Look Ahead: 

  • Exterior metal wall panel installation at building sector 2K to begin. 
  • MEPF hanger installation at building sectors 1A and 1B is ongoing. 
  • Installation of HVAC ductwork at building sector 1A on the second and third floors to continue.
  • Installation of interior metal stairs at Stair 2 to begin. 
  • Fireproofing at 1B sector to continue. 
  • TPO roof installation to begin. 

May 2022 

Past Month’s Accomplishments: 

  • Interior CMU block walls at stage completed. 
  • Concrete pouring of stage and stairs at gym completed. 
  • Primary steel erection at building sector 1B completed. 
  • Building perimeter knee wall construction and secondary steel installation at building sector 1A completed. 
  • Metal panel roof at building sector 2K completed. 
  • Secondary steel installation and building perimeter knee wall construction at building sector 2K is in progress. 
  • Installation of interior hat channel and MEPF hangers at building sector 2K in progress. 
  • Building foundation wall waterproofing and backfill in progress. 
  • MEPF Hangers, interior wall construction, and fireproofing at building sector 1A in progress. 
  • Stormwater utilities at SW corner in progress. 

30-Day Look Ahead: 

  • Exterior metal wall panel installation at building sector 1A to begin. 
  • MEPF hanger installation, interior wall framing, and one-siding with drywall in building sector 1A is ongoing. 
  • Installation of HVAC ductwork on first floor of building sector 1A to begin. 
  • Installation of interior metal stairs to begin. 
  • CMU bracing installation at building sector 2G is ongoing. 
  • Underground telecom ductbank installation at west side of site is ongoing. 
  • Roof parapet framing and blocking to continue. 
  • Concrete slab on metal deck pours on the second, third, and fourth floors in sector 1B to continue. 

April 2022 

Past Month’s Accomplishments: 

  • Pouring of elevated concrete deck in sector 1A on the third and fourth floors completed. 
  • Primary steel erection at sectors 2G and 2K completed. 
  • Interior CMU block elevator shaft walls completed. 
  • Grading of turf field area completed. 
  • Secondary steel installation at sector 1A in progress. 
  • Primary steel erection for sector 1B in progress. 
  • Building perimeter knee wall framing and sheathing at sector 1A in progress. 
  • Building foundation wall waterproofing and backfill in progress. 

30-Day Look Ahead: 

  • Exterior metal panel deliveries to begin. 
  • Metal panel roof installation at sectors 2G and 2K is ongoing. 
  • Exterior metal wall panel installation to begin. 
  • MEPF hanger installation at sector 1A to continue. 
  • Interior wall framing and one-siding with drywall at sector 1A is ongoing. 
  • Installation of stormwater utilities at SW corner to begin. 

March 2022 

Past Month’s Accomplishments: 

  • Pouring of sector 1A concrete slab on second floor metal deck completed. 
  • Steel detailing and secondary steel installation at sector 1A in progress. 
  • Primary steel erection at 2K in progress. 
  • MEP slab rough-in at the sector 1A elevated decks in progress. 
  • CMU walls in sector 2G and CMU elevator shaft in progress. 
  • Grading turf field in progress. 
  • Foundation wall damp-roofing and backfill in progress. 

30-Day Look Ahead: 

  • Building perimeter knee wall framing and AVB at sector 1A is ongoing. 
  • Roof parapet framing at sector 1A is ongoing. 
  • MEP Hangers and Interior Wall Layout at sector 1A to begin. 
  • Structural steel erection in sectors 2K, 2G, and 1B to continue. 
  • Façade metal panel deliveries to begin. 
  • Concrete slab on deck pours at sector 1A on the third and fourth floor to continue. 

February 2022 

Past Month’s Accomplishments: 

  • Pouring concrete building foundations at building sector 1B completed. 
  • Rough in under slab MEP utilities at building sector 1B completed. 
  • Concrete slab on grade pours at sector 2G and 2K completed. 
  • Concrete slab on grade preparation at sector 1B in progress. 
  • Structural steel erection in sector 1A in progress. 
  • CMU walls in sector 2G in progress. 

30-Day Look Ahead: 

  • Concrete slab on deck pours in sector 1A are ongoing. 
  • Structural steel erection in sectors 2K and 2G are ongoing. 
  • Exterior framing and sheathing to begin. 

January 2022 

Past Month’s Accomplishments: 

  • Sorting and hauling of existing building demolition debris complete. 
  • Pouring of concrete foundations at building sectors 2K, 2G, and 1A complete. 
  • Concrete slab on grade pours at sector 1A complete. 
  • Pouring of concrete building foundation footings, piers and walls at sector 1B in progress. 
  • Construction of site access roads and laydown areas underway. 
  • Installation of under slab utilities at building sectors 2G and 1B in progress. 
  • Structural steel deliveries in progress. 

30-Day Look Ahead: 

  • Concrete slab on grade pours at sectors 2G and 2K to continue. 
  • Under slab utilities at sector 1B to continue. 
  • Structural steel erection to begin. 

Year 2021

December 2021  

Past Month’s Accomplishments:  

  • Demolition of existing school completed. 
  • Pouring of concrete foundations at building Wings 2K & 1A completed. 
  • Installation of underground electrical duct bank completed. 
  • Sorting and hauling remaining existing school demolition debris in progress. 
  • Pouring concrete building foundation footings, piers & walls in Wings 2G and 1B in progress. 
  • Construction of site access roads and laydown areas in progress. 

30-Day Look Ahead: 

  • Installation of under slab utilities at Wings 2K & 1A to continue. 
  • Pouring of concrete building foundations at Wings 2G & 1B to continue. 
  • Slab on grade concrete pours at building Wings 2K & 1A is ongoing. 
  • Structural steel deliveries to begin. 

November 2021 

Past Month’s Accomplishments: 

  • Phase I and II of demolition for existing school completed. 
  • Phase III of demolition in progress. 
  • Clearing and grading of new building pad completed. 
  • Installation of new fence and erosion controls at Oliver Street completed. 
  • Construction of site access roads in progress. 

30-Day Look Ahead: 

  • Pouring of concrete building foundations will continue. 
  • First slab on grade pour will begin. 
  • Demolition of existing building will continue. 
  • Underslab utilities will continue. 

October 2021 

Past Month’s Accomplishments: 

  • Erosion and sediment control measures at site perimeter and construction entrances completed. 
  • Interior abatement at existing school completed. 
  • Demolition of the existing school in progress. 
  • Clearing and grading for the building pad ongoing. 

30-Day Look Ahead: 

  • Laying of concrete building foundations to begin. 
  • Under slab plumbing and electrical work to begin. 

August 2021 

Past Month’s Accomplishments: 

  • Site perimeter surveying and fencing completed. 
  • Installation of erosion and sediment control measures at the site perimeter, as well as construction entrances, are underway. 
  • Interior abatement underway. 

30-Day Look Ahead: 

  • Completion of site perimeter erosion and sediment control measures to begin. 
  • School demolition to begin. 
  • Tree and grass removal to begin. 
  • Grading of the site to commence. 
  • Construction of concrete building foundations to begin. 

Documents & Presentations

Project Fact Sheet

Project Update Meeting - 05/08/2023 | Recording; Presentation (English, Spanish, French); Q&A (English, Spanish, French)

Construction Update Meeting - 10/17/2022 | Recording; Presentation (English, Spanish, French); Q&A (English, Spanish, French)

Community Investment Program Town Hall - 04/2021 | Recording; Presentation (English, Spanish, French)

Swing Space Logistics Town Hall - 03/18/2021 | Presentation (English, Spanish, French)

Construction Site Logistics Town Hall - 01/12/2021 | Presentation (English, Spanish, French)

PGCPS Alternative Construction Finance Program Town Hall - 12/14/2020 | Presentation (English, Spanish, French)