December 2022
Past Month’s Accomplishments:
- In-wall MEP rough-in for sector 2B completed.
- Drywall close ins for sectors 1A and 2K completed.
- Drywall finishing in sector 1A completed.
- Hardware delivery received.
- Prime and first coat paint for sector 1B completed.
- Interior door frame installation completed.
- Installation of exterior aluminum storefront entrances completed.
- BGE transformer, final connection, and electrical room feeder cable pulls completed.
30-Day Look Ahead:
- Electrical in wall rough-ins for sector 2B to be completed.
- Installation of underground storm pipes for MH 24 – MH 25 – MH 27 to begin.
- Temporary heat installation to begin.
- Asphalt base paving at bus parking lot to begin.
- Drywall close-in in for sector 2B to begin.
- Priming and painting in sector 1A to begin.
- Hard ceiling inspection and close-in for sector 1B to be completed.
November 2022
Past Month’s Accomplishments:
- In-wall MEP Rough-in for sectors 1A and 2K completed.
- Drywall close-in at sector 1B completed.
- One-side drywall installation in sector 1A completed.
- Underground chilled water line pipe and interior gas line installation, as well as inspection, were completed.
30-Day Look Ahead:
- Electrical in-wall rough-ins for sectors 2A and 2B are ongoing.
- Underground storm pipe MH 24 – MH 25 – MH 27 to begin.
- Temporary heat installation to begin.
- Wall close-ins for sector 1A to be completed.
October 2022
Past Month’s Accomplishments:
- Exterior window installation at sector 2K completed.
- Construction of exterior electrical transformer pad completed.
- Installation of underground chilled water piping, interior building gas line, and exterior metal panels completed.
- In-wall MEP rough-ins for sectors 1A and 1B completed.
- One side drywall for sector 1B completed.
- All stairs except for main learning stairs completed.
- Underground sanitary line connection from kitchen to grease interceptor completed.
30-Day Look Ahead:
- Interior wall close-in inspections for sectors 1A and 1B to be completed.
- Hanging of drywall for sector 1A to continue.
- Overhead electrical rough-ins for level 2 of the building is ongoing.
- In-wall electrical rough-ins for sector 2B to continue.
- Constructions of underground storm lines MH 24, MH 25, and MH 27 to begin.
- RTU deliveries to site to be completed.
September 2022
Past Month’s Accomplishments:
- Spray fireproofing, setting of RTU curbs, canopy outriggers, and installation of primary electrical duct bank, as well as secondary duct bank, were completed.
- Interior stud wall framing in building for sector 2A completed.
- Overhead ductwork in building for sector 2B completed.
- Mechanical room equipment delivery to site completed.
- Electrical rough-in in building for sector 1B completed.
- In-wall HVAC controls rough-in for building sector 1 completed.
- Stair 2 installation completed.
- Storm line installation from MH 15 to MH 16 completed.
30-Day Look Ahead:
- Wall close-in inspections and hanging of drywall in building sector 1 are ongoing.
- Overhead MEP rough-in on level 2 of building sector 2 is ongoing.
- In-wall electrical rough-ins in building sectors 1A and 2B are ongoing.
- Door frame delivery is expected.
- Chiller, transformer, and generator pad installation is ongoing.
- Installation of storm lines MH 24, MH 25, and MH 27 to begin.
- Stair 3 installation to begin.
- IMP wall panels and storefront installation to be completed.
August 2022
Past Month’s Accomplishments:
- Spraying of fireproofing in building center and sector 2B completed.
- Interior stud wall framing in building sector 2B completed.
- Interior CMU block walls completed.
- Storefront on south and east elevation of building completed.
- Retaining wall #1, grease interceptor, and TPO roofing installation completed.
30-Day Look Ahead:
- Interior stud wall framing on level 2 of building sector 2A is ongoing.
- Delivery of electrical switchboards to be completed.
- Overhead MEP rough-in on level 2 of building sector 2A to begin.
- In-wall electrical rough-in is ongoing and in-wall close-in inspection and hanging of drywall to begin.
- Door frame delivery to be completed.
- Chiller, transformer, and generator pad installation to begin.
- Interior stair deliveries and installation is ongoing.
July 2022
Past Month’s Accomplishments:
- Backfill at the perimeter of the building completed.
- Interior stud wall framing at level 1 of sector 1A and sector 2K completed.
- Spraying of fireproofing in sectors 2K and 2G completed.
- Roof panel installation in sector 2G completed.
- Overhead and in-wall mechanical and plumbing rough-in on level 1 of sector 1B completed.
- Site underground sanitary utility piping completed.
30-Day Look Ahead:
- Spraying of fireproofing ceiling lath on level 2 of sector 1A and sector 1B to be completed.
- Interior stud wall framing at sector 1B on level 2 to begin.
- MEP ceiling and wall rough-in for building sector 2K and level 2 of 1B is ongoing.
- Installation of exterior wall panels in building sectors 1A and 2G is ongoing.
- Installation of site underground water and storm utilities to begin.
June 2022
Past Month’s Accomplishments:
- Brick masonry walls and backfill at the perimeter of the building completed.
- Ceiling hat channel and purlin bracing work and ceiling lath installation in 2K completed.
- Interior wall framing in level 1 of sector 1B completed.
- 70% of interior wall framing in level 1 of sector 1A completed.
- All MEPF hangers on sector 1A and second level of sector 1B completed.
- Fireproofing in sector 1B on level 1 and Sector 2G completed.
30-Day Look Ahead:
- Installation of fireproofing lath system in building sectors 1A on level 2, 1B on level 2, and 2K are ongoing.
- Interior wall framing in building sectors 1A and 2K are ongoing.
- MEP ceiling and wall rough-in for building sectors 1B on level 2 and 2K are ongoing.
- Interior CMU block walls and installation of the roof panels in building sector 2G to be completed.
- Installation of exterior wall panels in building sectors 1A, 1B, and 2K to continue.
- Installation of site sanitary sewer utility to be completed.
May 2022
Past Month’s Accomplishments:
- All secondary steel except for the canopy completed.
- Installation of the roof panels in building sectors 1A, 1B, and 2K completed.
- Fireproofing on level 1 of building sector 1B completed.
- MEPF hangers on level 1 of building sectors 1A, 1B, and sector 2K completed.
- Interior CMU block walls in building sector 2K completed.
- Building perimeter knee wall installation completed.
30-Day Look Ahead:
- Fireproofing of lath system and interior wall framing in building sectors 1A, 1B, and 2K is ongoing.
- MEP ceiling rough-in for building sector 2K is ongoing.
- MEPF hangers installation for building sectors 1A and 1B to be completed.
- Interior CMU block walls and installation of roof panels for building sector 2G to be completed.
- Installation of hat channel for building sector 1A to be completed.
- Exterior brick installation to be completed.
- Installation of exterior wall panels for building sectors 1B and 2K are ongoing.
- Installation of site sanitary sewer utility to be completed.
April 2022
Past Month’s Accomplishments:
- Installation of caissons at the south side of the site completed.
- Primary and secondary steel in sector 2G completed.
- Secondary steel wall girts and purlins at all building sectors completed.
- Roof decking and all elevated concrete deck pours completed.
- Roof panels in Sector 2K competed.
- Building perimeter knee wall installation in sectors 2k and 1B completed.
- Installation of MEP hangers in sector 2K and first floor of sector 1B completed.
30-Day Look Ahead:
- Interior wall layout and framing for sector 1B on the first floor is ongoing.
- Interior installation of ceiling hat channel and lath system in sector 2K is ongoing.
- Exterior waterproofing/AVB on sheathing/exterior brick at sector 2K to continue.
- Installation of wall panels in sector 2K to continue.
- Installation of the exterior sanitary sewer system to be completed.
- Installation of data/electrical duct banks is ongoing.
March 2022
Past Month’s Accomplishments:
- Concrete slab on grade in sector 2G and center infill completed.
- Primary and secondary steel in sector 2K completed.
- Primary steel in sectors 1A and 1B completed.
- Pouring of slab on metal deck in sector 1B completed.
- Secondary steel installation in sectors 1A, 1B, and Infills in progress.
- Knee wall installation and waterproofing around the perimeter of the building in progress.
30-Day Look Ahead:
- Metal decks, MEP prep, and concrete pours in sectors 1A and 1B to continue.
- Steel erection of sector 2G and center infill to be completed.
- Roof Panel Installation and exterior masonry walls in Sector 2K and 1B to begin.
- Interior layout of critical walls (MEP rooms, bathrooms, corridors) to begin.
- Main power duct bank run from existing school to new building will begin.
- MEP hangers and top track in sector 1B on the first floor will begin.
February 2022
Past Month’s Accomplishments:
- Concrete slab on grade in sectors 1A, 1B, and 2K completed.
- Steel erection in sectors 1A, 1B, and 2K in progress.
- Rough in underground MEP utilities for Sector 2G completed.
30-Day Look Ahead:
- Concrete building foundations in sector 2G to be completed.
- Steel erection in sectors 1A , 1B, and 2K to continue.
- Rough in under slab electrical for sector 2G to be completed.
- Concrete slab on grade preparation and pouring in sector 2G to be completed.
- Steel erection in sector 2G to begin.
- Elevated slab on deck placement in sectors 1A and 1B to begin.
January 2022
Past Month’s Accomplishments:
- Concrete building foundations in building sectors 2K, 1B and 1A completed.
- Underground site utilities in building sectors 2K, 1B and 80% of 1A completed.
- Elevator pit including walls, waterproofing and dirt backfill completed.
- Structural steel on site received and shakeout/inventory activities begun.
- Mobilization activities and assembly of the structural steel erection crane completed.
- Grading and setup of staging area for the stability piles on the south side of building completed.
- Site perimeter clearing activities completed.
30-Day Look Ahead:
- Pouring of concrete slab on grade at sectors 1A, 1B, and 2K ongoing.
- Underground building site utilities to be completed.
- Building of concrete foundations at sector 2G and learning stairs to be completed.
- Pouring of concrete slab on grade in for sectors 1A, 1B, and 2G to be completed.
- Erecting of structural steel at sectors 1A and 1B to begin.