Kenmoor Middle School

Status
Complete
Funding Model
P3
Project Type
New Construction
Budget
$67,000,000
Architect
Stantec
General Contractor
Gilbane Building Co.
Project Manager
Brailsford & Dunlavey

School Information

Principal
Rebecca Turner
Address
501 Kenmoor Dr, Landover, MD 20785
Neighborhood
Glenarden, Landover
School Board District
District 4
County Council District
District 5
State Legislative District
District 24

Project Timeline

Blueprint Project Timeline.png

Project Scope

Construction of a new 144,000 SF school with a capacity of 1,200 students at the back of the existing Kenmoor Middle School site.

News & Announcements

There are currently no announcements for this project.

Project Updates

Year 2023

August 2023 

Past Month’s Accomplishments: 

  • Final Cleaning completed. 
  • Owner Training completed. 
  • Final Inspections completed. 
  • MEP Commissioning completed. 
  • Main Entrance Canopy completed. 
  • Final Coat Asphalt / Striping completed. 
  • Landscaping completed. 
  • Exterior accent panel painting completed. 

30-Day Look Ahead: 

  • Punch list in progress. 
  • Owner training in progress.  

July 2023 

Past Month’s Accomplishments: 

  • Final Submerged Gravel for Wetland 1 and 2 completed. 
  • Carpet in Media Sector 1 completed. 
  • Learning Stair above ceiling baffle and devices completed. 
  • Wood flooring installation at Gym, Stage and Dance room completed. 
  • Dance floor sanded and finished completed. 
  • Dining furniture installation completed. 
  • Gym bleachers installation completed. 
  • MAU and KEF Start-up completed. 
  • TAB of RTUs completed. 
  • Window treatment installation completed. 
  • Production Studio completed. 

30-Day Look Ahead: 

  • Volleyball equipment installation to be completed. 
  • Gym court line stripping to be completed. 
  • Stage curtains and theatrical system to be completed. 
  • Asphalt topcoat to be completed. 
  • Asphalt basketball court to be completed. 
  • Seeding multipurpose field to be completed. 
  • Final cleaning of Sector 2 to be completed. 
  • Flagpole installation to be completed. 
  • Gym wall pads to be completed. 

June 2023 

Past Month’s Accomplishments: 

  • Bathroom partitions in Sector 1 completed. 
  • Collaborative ceiling baffles in sector 1 completed. 
  • Projection Screen for sector 2 completed. 
  • Storm line installation (MH-32 to I-38) completed. 
  • Submerged Underground Wetland #1 completed. 
  • Baseball field seeding completed. 
  • Exterior light poles completed. 
  • West parking lot base asphalt completed. 
  • FF&E Delivery for sector 1 classroom and offices completed. 
  •  Aluminum storefronts completed. 
  • Kitchen equipment delivery completed. 
  • Dining area VCT Flooring completed. 
  • Ceiling tile and acoustical ceiling diffusers for sector 2 completed. 
  • Acoustical ceiling panels (Gym, Dance, Band and Choral) completed. 
  • Smartboard installation and integration completed. 
  • BAS installation in wellness and dance rooms completed. 
  • Locker room tile completed. 
  • Canopy Erection completed. 
  • Exterior building sign completed. 
  • Operable partitions completed. 

30-Day Look Ahead: 

  • Gym flooring to begin. 
  • Overhead Coiling Doors to begin. 
  • Wood flooring installation for dance areas to start. 
  • Flagpole installation to be completed. 
  • Shade structure installation to start. 
  • Remainder of asphalt paving to start. 
  • Media Center carpeting to start. 
  • Gym Bleachers and Gym wall pads to be delivered. 
  • Multi-purpose field grading and grass is ongoing. 

May 2023 

Past Month’s Accomplishments: 

  • Final paint for sector 1 completed. 
  • Wall covering for sector 1 completed. 
  • Bathroom tile for sector 2 completed. 
  • Learning stair concrete completed. 
  • Media bulkhead paint, ceiling grid, fixtures, devices, and dropping tile completed. 
  • Smartboards delivered. 
  • Locker room drywall and finishing completed. 
  • Locker room locker bases completed. 
  • Dining area ceiling grid completed. 

30-Day Look Ahead: 

  • Asphalt paving for west parking lot to begin. 
  • Overhead of Coiling Doors to begin. 
  • Classroom operable partitions to be completed. 
  • Gym and Dance areas for wood flooring to be installed. 
  • Exterior building painting to begin. 
  • Flagpole installation anticipated to begin. 
  • Toilet accessories to start. 
  • Walk-in cooler and freezer quarry tile to be completed. 
  • MEP equipment start-up to continue. 
  • FF&E delivery and installation to begin. 
  • Window sills to begin. 
  • Window shades anticipated to begin. 
  • Mirrors anticipated to begin. 

April 2023 

Past Month’s Accomplishments:  

  • Gym basketball hoops and divider curtain completed. 
  • Gym stage paint completed. 
  • Ceiling grid, light fixture, and ceiling devices for Sector 2A completed. 
  • VCT flooring installation for Sector 2B and 2A completed. 
  • Kitchen quarry tile completed. 
  • Soil cemented and finished asphalt on second half of bus parking lot completed. 
  • Markerboards and tack boards installation completed. 
  • Learning stair steel completed. 
  • Storm pipe MH 25 – MH 27 completed. 
  • Sky light installation completed. 
  • Media ceiling, fixtures, and devices completed. 
  • Concrete retaining wall #2 completed. 
  • Power for RTU and VAV’s completed. 
  • Electrical Generator installation completed. 
  • Inspection for temporary use elevator completed. 
  • Locker installation for classroom wing completed. 
  • Interior glazing completed. 
  • Shade structure and flagpole footings completed. 

30-Day Look Ahead:     

  • Kitchen equipment installation to begin. 
  • Wall protection installation to begin. 
  • Overhead Coiling Doors to begin. 
  • Classroom operable partitions anticipated to begin. 
  • Wood flooring for Gym and Dance areas to begin. 
  • Steel erection for entrance canopy to begin. 
  • Baffle ceiling installation anticipated to begin. 
  • Curb and gutter installation are ongoing. 
  • Flagpole installation anticipated to begin. 
  • Porcelain tile in the locker room anticipated to begin. 

March 2023 

Past Month’s Accomplishments: 

  • Prime and paint in Sector 2A completed. 
  • Delivery of remaining RTUs completed. 
  • Delivery and setting of chiller completed. 
  • Gym overhead and wall painting completed. 
  • Gym acoustical ceiling panels completed. 
  • Ceiling grid, light fixtures, and ceiling devices in Sector 2B completed. 
  • VCT flooring installation for Sector 1A completed. 
  • Bathroom Ceramic Tile for Sector 2B and 2A completed. 
  • Half of the bus parking lot asphalt pave completed. 
  • Casework and tops for sector 2B and 2A completed. 
  • Science lab casework for academic classroom wing completed. 
  • Storm pipe MH24 – MH 25 completed. 

30-Day Look Ahead: 

  • Curb and gutter for bus parking lot anticipated to begin.  
  • Ceiling grid, light fixtures, and devices for Sector 2A to begin. 
  • Quarry tile for kitchen area to begin. 
  • Locker delivery and installation anticipated to begin. 
  • VCT Flooring installation for 2B and 2A to begin. 
  • Setting generator to be completed. 
  • Wood flooring delivery anticipated. 
  • RTU equipment start-up anticipated to begin. 
  • Entrance canopy anticipated to begin. 
  • MEP flushing and systems testing to continue. 

February 2023 

Past Month’s Accomplishments: 

  • Drywall close-in and interior wall finish for Stair 3 completed.  
  • Wall insulation and drywall close-in for Sector 2A completed. 
  • Prime and paint in Sector 2B completed. 
  • Fire/Smoke wall stencils completed. 
  • Kitchen hood installation completed. 
  • Ceiling grid and devices for Sector 1B completed. 
  • Ceiling grid and devices for Sector 1A completed. 
  • VCT flooring installation for Sector 1B completed. 
  • Bathroom Ceramic Tile for Sector 1B and 1A (except accent tile) completed. 
  • Skylight bulkhead framing completed. 
  • Drywall Close-in for library/media area completed. 
  • Bus parking lot grading completed. 
  • Casework and tops for sector 1B and 1A completed. 
  • Power and control connections to RTU and roof equipment completed. 

30-Day Look Ahead: 

  • Elevator cab testing and balancing are ongoing. 
  • Ceiling grid for Sector 2B is ongoing. 
  • Prime and painting for Sector 2K and 2G are ongoing. 
  • Installation of light fixtures in Sector 2B is ongoing. 
  • Work for storm pipe MH24 – MH 25 is ongoing. 
  • RTU connections to units are ongoing. 
  • Casework deliveries are ongoing. 
  • Finishing and taping for Sector 2A is ongoing. 
  • Labeling MEP overhead equipment is ongoing. 
  • In-wall rough-in for Dining and Sector 2G is ongoing. 
  • Light fixture rough-in for Sector 2G is ongoing. 
  • Electrical in-wall rough-in for Sector 2G to be completed. 
  • Bus parking lot curb and gutter is anticipated to begin. 
  • Asphalt base for the bus parking lot to begin. 
  • Ceiling grid, light fixtures, and devices for Sector 2B to begin. 
  • Bathroom tile for classroom Sector on level 2 to begin.  
  • Ceramic accent tiling to begin. 
  • Water tie-in connection to existing main anticipated to begin. 
  • Softball field grading anticipated to begin. 
  • Gym painting, acoustical wall panels, and light fixtures to begin. 
  • Balance of RTU delivery to be completed. 
  • Chiller pad and generator pad to be completed. 

January 2023 

Past Month’s Accomplishments: 

  • In-wall MEP rough-in for sector 2A completed. 
  • Drywall close-in in for sector 2B and sector 2K kitchen completed. 
  • Drywall finishing, prime, and first coat painting in sector 1A completed. 
  • Ceiling grid installation for sector 1B completed. 
  • Electrical panelboard connections completed. 
  • Overhead ductwork, installation of fire protection, and framing of sector 2G gym completed. 
  • Elevator cab installation completed. 

30-Day Look Ahead: 

  • Electrical in-wall rough-in for sector 2G gym to be completed. 
  • Bus parking lot curbs, gutters, and asphalt base to be completed. 
  • Drywall close-in for sector 2A to begin. 
  • Ceiling grid installation, priming, and painting for sector 2B to begin. 
  • Hard ceiling inspection and close-in for sector 1A to be completed. 
  • Ceiling grid installation for sector 2B to be completed. 
  • Installation for light fixtures drop ceiling in sector 1A to begin. 
  • Bathroom tile on level 1 of classroom sector to begin. 
  • Flooring in sector 1B to begin. 
  • Softball field grading to begin. 

Year 2022

December 2022 

Past Month’s Accomplishments: 

  • In-wall MEP rough-in for sector 2B completed. 
  • Drywall close ins for sectors 1A and 2K completed. 
  • Drywall finishing in sector 1A completed. 
  • Hardware delivery received. 
  • Prime and first coat paint for sector 1B completed. 
  • Interior door frame installation completed. 
  • Installation of exterior aluminum storefront entrances completed. 
  • BGE transformer, final connection, and electrical room feeder cable pulls completed. 

30-Day Look Ahead: 

  • Electrical in wall rough-ins for sector 2B to be completed. 
  • Installation of underground storm pipes for MH 24 – MH 25 – MH 27 to begin. 
  • Temporary heat installation to begin. 
  • Asphalt base paving at bus parking lot to begin. 
  • Drywall close-in in for sector 2B to begin. 
  • Priming and painting in sector 1A to begin. 
  • Hard ceiling inspection and close-in for sector 1B to be completed. 

November 2022 

Past Month’s Accomplishments: 

  • In-wall MEP Rough-in for sectors 1A and 2K completed. 
  • Drywall close-in at sector 1B completed. 
  • One-side drywall installation in sector 1A completed. 
  • Underground chilled water line pipe and interior gas line installation, as well as inspection, were completed. 

30-Day Look Ahead: 

  • Electrical in-wall rough-ins for sectors 2A and 2B are ongoing. 
  • Underground storm pipe MH 24 – MH 25 – MH 27 to begin. 
  • Temporary heat installation to begin. 
  • Wall close-ins for sector 1A to be completed. 

October 2022 

Past Month’s Accomplishments: 

  • Exterior window installation at sector 2K completed. 
  • Construction of exterior electrical transformer pad completed. 
  • Installation of underground chilled water piping, interior building gas line, and exterior metal panels completed. 
  • In-wall MEP rough-ins for sectors 1A and 1B completed. 
  • One side drywall for sector 1B completed. 
  • All stairs except for main learning stairs completed. 
  • Underground sanitary line connection from kitchen to grease interceptor completed. 

30-Day Look Ahead: 

  • Interior wall close-in inspections for sectors 1A and 1B to be completed. 
  • Hanging of drywall for sector 1A to continue. 
  • Overhead electrical rough-ins for level 2 of the building is ongoing. 
  • In-wall electrical rough-ins for sector 2B to continue. 
  • Constructions of underground storm lines MH 24, MH 25, and MH 27 to begin. 
  • RTU deliveries to site to be completed. 

September 2022 

Past Month’s Accomplishments: 

  • Spray fireproofing, setting of RTU curbs, canopy outriggers, and installation of primary electrical duct bank, as well as secondary duct bank, were completed. 
  • Interior stud wall framing in building for sector 2A completed. 
  • Overhead ductwork in building for sector 2B completed. 
  • Mechanical room equipment delivery to site completed. 
  • Electrical rough-in in building for sector 1B completed. 
  • In-wall HVAC controls rough-in for building sector 1 completed. 
  • Stair 2 installation completed. 
  • Storm line installation from MH 15 to MH 16 completed. 

30-Day Look Ahead: 

  • Wall close-in inspections and hanging of drywall in building sector 1 are ongoing. 
  • Overhead MEP rough-in on level 2 of building sector 2 is ongoing. 
  • In-wall electrical rough-ins in building sectors 1A and 2B are ongoing. 
  • Door frame delivery is expected. 
  • Chiller, transformer, and generator pad installation is ongoing. 
  • Installation of storm lines MH 24, MH 25, and MH 27 to begin. 
  • Stair 3 installation to begin. 
  • IMP wall panels and storefront installation to be completed. 

August 2022 

Past Month’s Accomplishments: 

  • Spraying of fireproofing in building center and sector 2B completed. 
  • Interior stud wall framing in building sector 2B completed. 
  • Interior CMU block walls completed. 
  • Storefront on south and east elevation of building completed. 
  • Retaining wall #1, grease interceptor, and TPO roofing installation completed. 

30-Day Look Ahead: 

  • Interior stud wall framing on level 2 of building sector 2A is ongoing. 
  • Delivery of electrical switchboards to be completed. 
  • Overhead MEP rough-in on level 2 of building sector 2A to begin. 
  • In-wall electrical rough-in is ongoing and in-wall close-in inspection and hanging of drywall to begin. 
  • Door frame delivery to be completed. 
  • Chiller, transformer, and generator pad installation to begin. 
  • Interior stair deliveries and installation is ongoing. 

July 2022 

Past Month’s Accomplishments: 

  • Backfill at the perimeter of the building completed. 
  • Interior stud wall framing at level 1 of sector 1A and sector 2K completed. 
  • Spraying of fireproofing in sectors 2K and 2G completed. 
  • Roof panel installation in sector 2G completed. 
  • Overhead and in-wall mechanical and plumbing rough-in on level 1 of sector 1B completed. 
  • Site underground sanitary utility piping completed. 

30-Day Look Ahead: 

  • Spraying of fireproofing ceiling lath on level 2 of sector 1A and sector 1B to be completed. 
  • Interior stud wall framing at sector 1B on level 2 to begin. 
  • MEP ceiling and wall rough-in for building sector 2K and level 2 of 1B is ongoing. 
  • Installation of exterior wall panels in building sectors 1A and 2G is ongoing. 
  • Installation of site underground water and storm utilities to begin. 

June 2022 

Past Month’s Accomplishments: 

  • Brick masonry walls and backfill at the perimeter of the building completed. 
  • Ceiling hat channel and purlin bracing work and ceiling lath installation in 2K completed. 
  • Interior wall framing in level 1 of sector 1B completed. 
  • 70% of interior wall framing in level 1 of sector 1A completed. 
  • All MEPF hangers on sector 1A and second level of sector 1B completed. 
  • Fireproofing in sector 1B on level 1 and Sector 2G completed. 

30-Day Look Ahead: 

  • Installation of fireproofing lath system in building sectors 1A on level 2, 1B  on level 2, and 2K are ongoing. 
  • Interior wall framing in building sectors 1A and 2K are ongoing. 
  • MEP ceiling and wall rough-in for building sectors 1B on level 2 and 2K are ongoing. 
  • Interior CMU block walls and installation of the roof panels in building sector 2G to be completed. 
  • Installation of exterior wall panels in building sectors 1A, 1B, and 2K to continue. 
  • Installation of site sanitary sewer utility to be completed. 

May 2022 

Past Month’s Accomplishments: 

  • All secondary steel except for the canopy completed. 
  • Installation of the roof panels in building sectors 1A, 1B, and 2K completed. 
  • Fireproofing on level 1 of building sector 1B completed. 
  • MEPF hangers on level 1 of building sectors 1A, 1B, and sector 2K completed. 
  • Interior CMU block walls in building sector 2K completed. 
  • Building perimeter knee wall installation completed. 

30-Day Look Ahead: 

  • Fireproofing of lath system and interior wall framing in building sectors 1A, 1B, and 2K is ongoing. 
  • MEP ceiling rough-in for building sector 2K is ongoing. 
  • MEPF hangers installation for building sectors 1A and 1B to be completed. 
  • Interior CMU block walls and installation of roof panels for building sector 2G to be completed. 
  • Installation of hat channel for building sector 1A to be completed. 
  • Exterior brick installation to be completed. 
  • Installation of exterior wall panels for building sectors 1B and 2K are ongoing. 
  • Installation of site sanitary sewer utility to be completed. 

April 2022 

Past Month’s Accomplishments: 

  • Installation of caissons at the south side of the site completed. 
  • Primary and secondary steel in sector 2G completed. 
  • Secondary steel wall girts and purlins at all building sectors completed. 
  • Roof decking and all elevated concrete deck pours completed. 
  • Roof panels in Sector 2K competed. 
  • Building perimeter knee wall installation in sectors 2k and 1B completed. 
  • Installation of MEP hangers in sector 2K and first floor of sector 1B completed. 

30-Day Look Ahead: 

  • Interior wall layout and framing for sector 1B on the first floor is ongoing. 
  • Interior installation of ceiling hat channel and lath system in sector 2K is ongoing. 
  • Exterior waterproofing/AVB on sheathing/exterior brick at sector 2K to continue. 
  • Installation of wall panels in sector 2K to continue. 
  • Installation of the exterior sanitary sewer system to be completed. 
  • Installation of data/electrical duct banks is ongoing. 

March 2022 

Past Month’s Accomplishments: 

  • Concrete slab on grade in sector 2G and center infill completed. 
  • Primary and secondary steel in sector 2K completed. 
  • Primary steel in sectors 1A and 1B completed. 
  • Pouring of slab on metal deck in sector 1B completed. 
  • Secondary steel installation in sectors 1A, 1B, and Infills in progress. 
  • Knee wall installation and waterproofing around the perimeter of the building in progress. 

30-Day Look Ahead: 

  • Metal decks, MEP prep, and concrete pours in sectors 1A and 1B to continue. 
  • Steel erection of sector 2G and center infill to be completed. 
  • Roof Panel Installation and exterior masonry walls in Sector 2K and 1B to begin. 
  • Interior layout of critical walls (MEP rooms, bathrooms, corridors) to begin. 
  • Main power duct bank run from existing school to new building will begin. 
  • MEP hangers and top track in sector 1B on the first floor will begin. 

February 2022 

Past Month’s Accomplishments: 

  • Concrete slab on grade in sectors 1A, 1B, and 2K completed. 
  • Steel erection in sectors 1A, 1B, and 2K in progress. 
  • Rough in underground MEP utilities for Sector 2G completed. 

30-Day Look Ahead: 

  • Concrete building foundations in sector 2G to be completed. 
  • Steel erection in sectors 1A , 1B, and 2K to continue. 
  • Rough in under slab electrical for sector 2G to be completed. 
  • Concrete slab on grade preparation and pouring in sector 2G to be completed. 
  • Steel erection in sector 2G to begin. 
  • Elevated slab on deck placement in sectors 1A and 1B to begin. 

January 2022 

Past Month’s Accomplishments: 

  • Concrete building foundations in building sectors 2K, 1B and 1A completed. 
  • Underground site utilities in building sectors 2K, 1B and 80% of 1A completed. 
  • Elevator pit including walls, waterproofing and dirt backfill completed. 
  • Structural steel on site received and shakeout/inventory activities begun. 
  • Mobilization activities and assembly of the structural steel erection crane completed. 
  • Grading and setup of staging area for the stability piles on the south side of building completed. 
  • Site perimeter clearing activities completed. 

30-Day Look Ahead: 

  • Pouring of concrete slab on grade at sectors 1A, 1B, and 2K ongoing. 
  • Underground building site utilities to be completed. 
  • Building of concrete foundations at sector 2G and learning stairs to be completed. 
  • Pouring of concrete slab on grade in for sectors 1A, 1B, and 2G to be completed. 
  • Erecting of structural steel at sectors 1A and 1B to begin. 

Year 2021

December 2021 

Past Month’s Accomplishments: 

  • Installation of site access roads, material laydown area, and crane roads completed. 
  • Delivery of all structural steel deck and joists completed. 
  • Delivery of Classroom Wings 1A and 1B, as well as Kitchen Wing 2K infill structural steel columns and beams, were completed. 
  • Building foundations in Kitchen Wing 2K completed. 

30-Day Look Ahead: 

  • All site clearing at the site perimeter and temporary storm piping installation to be completed. 
  • Rough in under-slab utilities in Wings 2K, 1B, and 1A to be completed. 
  • Pouring of concrete slab on grade at Wings 2K, 1B, and 1A to begin. 
  • Concrete foundations at Classroom Wing 1A to be completed. 
  • Concrete foundations at Gym Wing 2G to begin. 

November 2021 

Past Month’s Accomplishments: 

  • Cutting and hauling-off to establish rough grading at building pad sector 1 completed. 
  • Temporary construction parking area installed. 
  • Concrete trade contractor mobilized and first rebar delivery received. 
  • Construction of haul road around building pad underway. 
  • Pouring of concrete building foundations on south side of building pad in progress. 
  • Clearing of trees at south side of site in progress. 
  • Filling for remaining area of building pad to prepare for concrete foundations in progress. 

30-Day Look Ahead: 

  • Building pad rough grading to be completed. 
  • Pouring of concrete building foundations will continue. 
  • Clearing of soils around site and construction of haul road/laydown areas to be completed. 
  • Installation of under-slab utilities will begin. 
  • Installation of underground electrical duct bank to be completed. 

October 2021 

Past Month’s Accomplishments: 

  • Erosion and sediment control measures at perimeter and onsite completed. 
  • Clearing & grading of building pad underway. 
  • Installation of temporary site roads and worker parking area in progress. 

30-Day Look Ahead: 

  • Importing and exporting of dirt for the building pad to be completed 
  • Laying of concrete building foundations to begin. 
  • Under slab plumbing and electrical work to begin. 

August 2021 

Past Month’s Accomplishments: 

  • Site perimeter surveying and fencing completed. 
  • Installation of temporary electricity to jobsite completed. 
  • Installation of erosion and sediment control measures at site perimeter and construction entrances underway. 

30-Day Look Ahead: 

  • Site perimeter erosion and sediment control measures to be completed. 
  • Tree and grass removal to begin. 
  • Rough grading of the site to begin. 
  • Grading of the building pad to begin. 
  • Construction of concrete building foundations to begin. 

Documents & Presentations

Project Fact Sheet

Project Update Meeting - 05/04/2023 | Recording; Presentation (English, Spanish, French, Dari, Pashto); Q&A (English, Spanish, French, Dari, Pashto, Arabic)

Construction Update Meeting - 10/11/2022 | Recording; Presentation (English, Spanish, French, Dari, Pashto); Q&A (English, Spanish, French, Dari, Pashto, Arabic)

Community Investment Program Town Hall - 04/2021 | Recording; Presentation (English, Spanish, French, Dari, Pashto)

Construction Site Logistics Town Hall - 01/25/2021 | Presentation (English, Spanish, French, Dari, Pashto)

PGCPS Alternative Construction Finance Program Town Hall - 12/16/2020 | Presentation (English, Spanish, French, Dari, Pashto)