Below, you will find Prince George’s County Public School’s (PGCPS) plan for remedial measures in response to the release of the Office of Legislative Audits Report (OLA) in March of 2025. The OLA Audit contained 16 findings which required remedial work on the part of PGCPS. PGCPS’s detailed remedial plan contained multiple steps toward improving every finding along with deadlines for each such remedial step. The overall purpose of this plan is to ensure Prince George’s County Schools are entirely in compliance with the relevant standards outlined in the OLA Report.
In order to provide full transparency, PGCPS will publish on its website quarterly progress reports for each finding listed in the OLA Report. The progress report will list each Finding and give a color-coded status of the progress to date. Below are the color codes:
Green=completed, on schedule
Yellow=completed, behind schedule
Blue=in progress, on track
Orange=lagging, but no missed deadline
Red=implementation is late
Some of the OLA Findings were “Repeat Findings” meaning the Finding or some portion of the Finding appeared in an earlier OLA Audit Report. These will be identified.
|
Finding |
New or Repeat |
Finding Summary |
Corrective Action Plan |
Division Responsible |
Status |
Comment |
|
Finding 1 |
Repeat |
Certain requirements of State law and recognized best practices were not incorporated into PGCPS’ procurement policies and were not consistently used when participating in intergovernmental cooperative purchasing agreements (ICPA). |
The Purchasing Department will revise the Administrative Procedure 3323 and the Purchasing and Supplies Manual to align with the revised Board Policy 3323, as it relates to intergovernmental cooperative purchasing agreements (ICPA). |
Purchasing/Office of Government Relations Compliance and Procedures |
Blue=in progress, on track |
The Policy and Governance Committee has revised the Purchasing policy to include the required language regarding ICPAs. The policy is currently going through the Board of Education’s review process. |
|
Finding 2 |
Repeat |
PGCPS did not always prepare written justifications, obtain Board approval, or publish contract awards for sole source procurements on eMaryland Marketplace Advantage (eMMA) as required. |
The Purchasing Department will revise the Administrative Procedure 3323 and the Purchasing and Supplies Manual to align with the revised Board Policy 3323. The Purchasing Department must include all of the justifications that are required by COMAR 21.05.05.02-04. |
Purchasing |
Blue=in progress, on track
Blue=in progress, on track
|
The Policy and Governance Committee has revised the Purchasing policy to include the required language regarding obtaining Board approval, or publish contract awards for sole source procurements on eMaryland Marketplace. See comment above. |
|
Any sole course contract that is at or above the thresholds identified in the policy, must be presented to the board for approval. |
Blue=in progress, on track |
The policy is currently going through the Board of Education’s review process. |
||||
|
Finding 3 |
New |
PGCPS did not execute formal written contracts and did not obtain approval from the Board for special education services. |
A formal written contract will be executed with each MSDE approved non-public school. However, competitive bidding will not be required. |
Academics/Special Education |
Blue=in progress, on track
|
On August 21, 2025, the Board of Education approved the use of multi-vendor non-public contracts to secure services for students with disabilities placed in nonpublic school settings. |
|
At the beginning of the school year a report shall be provided to the board that includes a comprehensive list of all approved non-public placements and projected costs, for that school year. |
Blue=in progress, on track |
PGCPS has submitted contracts to a total of 30 schools. Of those, 20 schools have returned their signed contracts, which have been forwarded for processing with the Department of Purchasing and Supply. PGCPS is currently awaiting contract signatures from the remaining 10 schools. |
||||
|
At the conclusion of the fiscal year, a detailed report shall be provided to the board detailing all of the expenditures to the non-public placements for the just concluded fiscal year. |
Blue=in progress, on track |
PGCPS is making the final edits to the contract template. |
||||
|
Finding 4 |
Repeat |
PGCPS did not analyze, or otherwise limit, the number of time records supervisors were reviewing and approving. We identified certain supervisors who routinely approved a large number of time records each pay period. |
By October 2025, the Chief Financial Officer and the Chief Information Technology Officer will work collaboratively to identify a system that would allow the time approver to delegate time cards to an alternate person in order to reduce the number of time cards the time approver is responsible for approving. Any costs involved in the purchase and utilization of this system will be incorporated into the FY 2026-2027 school budget. Implementation of the new system will occur during the 2026-2027 academic year. |
IT/Business Management Services |
Blue=in progress, on track |
The RFP was reissued and the selection committee is currently reviewing proposals for the new Enterprise Resource Planning (ERP) system. Upon Board approval in August 2026, the kickoff will begin in September 2026. Aligned with standard industry practices for implementation, the ERP upgrade is expected to be completed in FY2029. |
|
Finding 5 |
Repeat |
Critical human resources and payroll transactions were not always subject to a documented independent supervisory review. |
Preventive measures were established to prevent inaccurate amounts or data from being entered into the payroll fields. Additional staff, to include supervisory level staff, were assigned in the independent review process for salary adjustments calculations. Additional reports were developed to capture discrepancies for biweekly and substitute payrolls and additional payroll runs. |
Business Management Services |
Completed July 12, 2023 |
We have developed a preventative automated process to calculate salary adjustments, payout amounts, and retroactive payments, which prevents inaccurate amounts or data from being entered into payroll fields. |
|
IT implemented a data catch point for payroll fields to ensure data entry is accurate upon entry, including reviewing previously processed pay adjustment for propriety. |
Information Technology |
Completed October 8, 2025 |
||||
|
Currently we are working on an automated process to calculate salary adjustments, payout amounts, and retroactive payments. |
Business Management Services/IT |
Blue=in progress, on track |
The Payroll Department finalized the review of the pay elements and have reviewed the guidance from the selected vendor. This was finalized on January 5, 2026. We are actively working with IT to implement the EVP module in the selected vendor. We anticipate this to be completed by July 1, 2026. All future activities and updates will be identified, scheduled, and tracked after the July 2026 date. |
|||
|
The language below will be incorporated into the Employee Code of Conduct for the 2025-2026 academic year: “Complete work assignments accurately and in an appropriate, satisfactory, and timely manner.”Corrective action will be provided following the defined PGCPS disciplinary action process. |
Office of Government Relations Compliance and Procedures |
Completed August 1, 2025
|
||||
|
Finding 6 |
Repeat |
Internal controls and record keeping related to Transportation Department bus driver and bus attendant payrolls were not adequate to ensure the propriety of salary payments. |
Transportation Services has revised the daily operational payroll process to enhance accuracy and accountability. This includes clearly defining the roles and responsibilities of staff involved in payroll entry, review, and approval. To support these improvements, Transportation Services has initiated a review of electronic logging systems with current vendors to enhance payroll tracking and reporting. Additionally, a monthly audit sample review of overtime reports is being implemented. This review utilizes GPS data and internal documentation to verify the accuracy of overtime payments and ensure compliance with payroll procedures. |
Transportation Services/Business Management Services |
Completed July 1, 2024
|
Effective July 1, 2024, the Transportation Department implemented a standardized internal control process to strengthen accountability and ensure the accuracy and propriety of salary payments for bus drivers and bus attendants. This process is fully operational and consistently applied across all transportation sites.
|
|
Transportation Services is developing and working to implement a training plan to ensure efficacy is reached. |
Completed April 1, 2026 |
Transportation Services has implemented a structured training and onboarding plan designed to ensure staff proficiency and operational efficacy in payroll and related processes. This plan is now a standard component of onboarding for all new staff assigned to payroll-related responsibilities and is consistently applied across all transportation sites. |
||||
|
Finding 7 |
New |
PGCPS did not always perform a newly required screening for positions involving direct contact with minors. |
PGCPS will begin sending complaints to MSDE in instances where prior employers do not return the required form. PGCPS has historically not sent complaints to the state regarding the lack of return of the forms, which would address the lack of return, and provide PGCPS with additional documentation of the attempts to secure the form. |
Human Resources |
Completed March 1, 2025
|
The PGCPS Background Unit, effective March 1, 2025, began sending complaints to MSDE in instances where prior employers do not return the required form. |
|
As of August 2024, the process has been moved fully into e-signature services, which allows for better tracking and ease of recipient employer signature and return. Our selected e-signature service also sends out automatic reminders until completed. |
Our Office of Human Resources now reports to MSDE all instances in which employers do not respond within 20 business days. This same process is followed for international applicants. |
|||||
|
The Background Unit is exploring a manageable process for filing MSDE complaints for unreturned forms. |
Our Office of Human Resources now reports to MSDE all instances in which employers do not respond within 20 business days. This same process is followed for international applicants. |
|||||
|
Finding 8 |
Repeat |
PGCPS did not complete physical inventories of equipment every three years and resolve missing items from technology equipment inventories in a timely manner as required. |
IT/BMS is finalizing a plan to be completed in Fall of 2025 to conduct physical inventories of all technologies every three years, in all schools and central offices to align with the Assets Operating Manual. The plan will be implemented beginning January 2026. |
Information Technology/Business Management Services |
Blue=in progress, on track
|
In addition to the two BMS inventory specialists, Information Technology has hardware inventory associates who have contributed to the review of the asset manual and the asset management process. The Assets Operating Manual is scheduled to be completed by May 1, 2026. It is currently in final review. The review was intensive, starting with the Assistant Controller, Accounting Analyst III, Accountant II, and the Inventory Control Specialists. After making initial revisions/modifications, the manual was sent to all interested parties to review for their areas of responsibility. Those comments were incorporated into the manual. In addition, there were several meetings discussing the manual and those changes made to it. The monthly inventories are housed on the Accounting shared drive. |
|
Completed January 1, 2026
|
Reconciled physical inventory results with the selected vendor fixed assets utilizing barscan as the primary inventory management tool; researched and resolved variances and also submitted findings for management evaluation and review on November 14, 2025. |
|||||
|
IT developed an Attestation and Inventory Loss Form to list missing equipment identified during physical inventories of schools. Once the Attestation and Inventory Loss form is reviewed and signed by the building administrator, missing equipment items from schools are removed from the building's inventory in asset management. IT will document and replicate a similar process to investigate and resolve missing equipment from central offices beginning in January 2026. |
Information Technology |
Blue=in progress, on track |
IT has developed and utilized the attestation and loss form multiple times this school year. The draft of the written implementation/action plan was developed and finalized. The communication plan has also been developed. A meeting to communicate the plan was initially delayed. IT will share the plan with schools at the end of this school year. To complete physical inventory of all hardware in all locations, elementary and middle school staff will be asked to conduct inventory and submit documentation to the hardware inventory team who will cross check the data. |
|||
|
Finding 9 |
Redacted |
Information Technology |
||||
|
Finding 10 |
Redacted |
Information Technology |
||||
|
Finding 11 |
Redacted |
Information Technology |
||||
|
Finding 12 |
New |
PGCPS improperly used an intergovernmental cooperative purchasing agreement (ICPA) to procure a school bus camera system contract resulting in a lack of assurance that it obtained the best value. |
Going forward, the Transportation Department will work to ensure that all transportation contracts comply with State law and Board Policy 3323. |
Transportation/Purchasing |
Blue=in progress, on track |
Currently, Transportation is reviewing a new contract. It should be on the agenda for the May school board meeting. |
|
Finding 13 |
Repeat |
PGCPS did not use its automated bus routing software to periodically perform a system-wide analysis of routes and related bus capacities to maximize efficiency. In addition, PGCPS had not established comprehensive bus routing procedures. |
PGCPS secured a new routing system that enabled the department to create routes with defined start/end times that provided the necessary information for maximum efficiency and budget terms. The department has also prioritized creating routing procedures. |
Transportation |
Completed as of August 2024 |
|
|
The new routing system allows PGCPS to establish seat capacity limits, set maximum ridership goals, and define ride time limits. Reports are generated to ensure accuracy. Due to ongoing bus driver shortages, trips are continuously reviewed for optimal efficiency. |
Transportation |
Completed as of August 2024 |
||||
|
Finding 14 |
Redacted |
Information Technology |
||||
|
Finding 15 |
New |
PGCPS did not obtain and review claim data to support amounts invoiced by its third-party administrators (TPA) or audit healthcare claims activity paid by the TPA to ensure they were proper. |
PGCPS will identify an external Accounting Firm specializing in self-insured health plans to conduct a best practice claims and eligibility audit each calendar year. |
Business Management Services |
Completed as of December 2025 |
To ensure fiscal accountability and contractual compliance, PGCPS has engaged a third-party to audit the claims processing operations of its contracted TPAs. As experts in self-insured health plan oversight, this third-party will evaluate whether claims have been adjudicated in accordance with plan provisions, contractual obligations, and regulatory requirements. If this third-party identifies deviations from agreed-upon performance standards, PGCPS is prepared to initiate corrective actions and seek appropriate restitution from the service providers. |
|
Finding 16 |
New |
PGCPS did not apply for available School Resource Officer (SRO) grant funding through the Maryland Center for School Safety (MCSS) to offset the cost of school resource officers for fiscal years 2021 through 2024. |
The Office of School Safety and Security will coordinate with the police department and apply for MCSS grants in the future to offset costs. |
Operations/Office of School Safety and Security |
Completed as of December 2025 |
Each year, the PGCPS Chief Operating Officer will draft a letter explaining why the district opted not to apply for specific MCSS SRO grants, while also detailing the grants that were pursued. |